Construction site diary app
Crate's site diary app lets site managers and supervisors write the site diary on their phone, as things happen. Every entry is saved with who wrote it and when, and once it is submitted it appears in that site's diary for everyone with access to the site.
- Written on a phone
- Named and time-stamped
- One diary for each site

Site managers and supervisors write entries from wherever they are on site.
Every entry is saved with who wrote it and when.
Submitted entries appear in that site's diary straight away.
Everyone with access to the site sees the same diary.
How a site diary app works in Crate: one day on Riverside Quarter
Follow one day of the Riverside Quarter diary, from site open to the end of day check.
- 07:30Daniel Hughes, site managerSite opened. Gates unlocked and welfare cabins checked.
- 11:10Mark Davies, supervisorTimber delivery received at Gate 2 and checked against the delivery note.
- 15:45Stuart Hill, supervisorClient's project manager on site 15:00 to 15:40, walked levels 1 and 2.
- 17:49Daniel Hughes, site managerWorking area left secured. All plant and equipment left stationary and switched off. Timber delivered and stored in C8, storage area.
-
07:30
Site open
Daniel Hughes opens Riverside Quarter and writes the first entry of the day on his phone. It is saved with his name and the time.
Site openEntry by Daniel Hughes -
11:10
A delivery comes in
Mark Davies logs the timber delivery from the gate as it arrives. Once he submits it, the entry is in the site diary for everyone with access to the site.
Delivery loggedEntry by Mark Davies -
15:45
A visitor on site
Stuart Hill notes the client's project manager walking levels 1 and 2. The entry sits in the diary with Stuart's name and the time he wrote it.
Visitor notedEntry by Stuart Hill -
17:49
The end of day check
Daniel writes the end of day entry: working area secured, plant switched off, timber stored in C8. The day's record is complete, written as it happened.
Site securedEnd of day check logged
What is a site diary app?
A construction site diary is the day by day record of what happened on a site: who was there, what work was done, what was delivered, who visited and anything that went wrong. A site diary app lets the site team write that record on a phone instead of in a paper day book.
Paper day books are often written up at the end of the day, or the end of the week, from memory. They live in the site cabin, can be hard to read, and are rarely in the office when a client, a claim or an investigation needs them.
With Crate's site diary app, site managers and supervisors write entries as things happen. Each entry is saved with who wrote it and when, and once submitted it appears in that site's diary for everyone with access to the site.
What a site diary in Crate gives you
- Entries written on a phone
- The author's name on every entry
- The date and time of every entry
- One diary for each site
- Entries visible to everyone with access to the site
- End of day checks, deliveries and storage in one record
Entries are written as things happen, not pieced together at the end of the week.
One site diary app for the site and the office
Site managers and supervisors write entries on site. Everyone with access to the site sees them in the diary. Each day builds into its own record.
Every entry, in time order
Open a site's diary and see each day's entries in the order they were written, with the time, who wrote them and what they recorded. Earlier days sit alongside, a click away.
Write the entry where it happens
Site managers and supervisors write diary entries on their phone, out on site. Their name and the time are saved with the entry, so nobody has to remember to add them.
- Written on a phone, out on site
- The author's name saved with every entry
- The date and time saved with every entry
A dated record of every day
Each day's entries add up to a record for the site: every entry in time order, with who wrote it and when. It is the record people ask for when a question comes up months later.
- Every entry with its time
- The author's name on each entry
- One record for each site and day
The Building Safety Act raised the bar for site records
The Building Safety Act brought in new duties for everyone carrying out building work in England, and a stricter regime for higher-risk buildings: those at least 18 metres or 7 storeys with at least 2 residential units, and hospitals and care homes. On those buildings, the client must keep golden thread information electronically, accurate and up to date, and those carrying out the work help maintain it.
A site diary is not the golden thread. But entries written on the day, by named people, are dated evidence of what happened on site and when. Crate keeps that record for every site, so it can support golden thread information and your Building Safety Act evidence.
Crate keeps a dated diary for each site, with who wrote each entry and when. It is not a golden thread system and does not make a project compliant. Take advice on what your projects need to keep.
"The client must ensure the golden thread information… is kept in an electronic format… is accurate and up to date…"
Building (Higher-Risk Buildings Procedures) (England) Regulations 2023, regulation 31(2)
Last updated October 2026
What to record in a construction site diary
General good practice for a site diary that will stand up when someone asks what happened.
| What to record | Why it matters |
|---|---|
| Date and weather | Weather explains lost time and affects work such as concrete pours, roofing and lifting. |
| Who was on site | Shows which trades were working each day, which helps with progress, safety and any dispute later. |
| Work done | A plain record of what was done and where, to track progress against the programme. |
| Deliveries | What arrived, when, and where it was stored, so materials can be traced later. |
| Visitors | Clients, inspectors, designers and anyone else who came to site, and why. |
| Delays and their causes | Weather, late information, access problems or missing materials, recorded on the day they happen. |
| Instructions received | Verbal or written instructions, with who gave them and when. |
| Incidents | Accidents, near misses and dangerous occurrences, noted alongside the formal report. |
| End of day checks | How the site was left: work areas secured, plant switched off, gates locked. |
What you record will depend on your contract, the project and your company procedures.
Paper day books versus a site diary app
The same daily record, written at the time and kept where the whole team can see it.
| Question | Paper day book | Site diary app in Crate |
|---|---|---|
| Where it is written | In a book in the site cabin | On a phone, wherever you are on site |
| When it is written | Often at the end of the day, from memory | As things happen |
| Who wrote it | A signature, if you can read it | The author's name saved with every entry |
| When it was written | A date at the top of the page | The date and time saved with every entry |
| Who can see it | Whoever has the book | Everyone with access to the site |
| When the office needs it | A trip to site, or a photo of a page | Already in the site's diary |

Submitted, and in the site diary
When a site manager submits an entry, it is logged and appears in that site's diary for everyone with access to the site. Project managers and head office can see what happened on site without waiting for paperwork to come back.
- Entries logged as soon as they are submitted
- Visible to everyone with access to the site
- No paperwork to send back from site
Questions about the site diary app
Straight answers to what construction teams ask us most.
What is a site diary app?
A site diary app is a digital version of the construction site diary, written on a phone instead of in a paper day book. In Crate, site managers and supervisors write diary entries on their phone, and each entry is saved with who wrote it and when.
What should a construction site diary include?
Most include the date and weather, who was on site, the work done, deliveries, visitors, delays and their causes, instructions received, incidents and end of day checks. What you record depends on your contract and your company procedures.
Who writes the site diary in Crate?
Site managers and supervisors write diary entries on their phone. Each entry is saved with the name of the person who wrote it, so it is always clear who recorded what.
Who can see the site diary?
Once an entry is submitted, it appears in that site's diary for people with access to the site, such as the site team, project managers or head office.
Is a site diary a legal requirement?
There is no general law that says every construction site must keep a diary, but your contract or company procedures may require one. A record written at the time is useful evidence if questions are asked later about progress, delays or safety. Take advice on what your contracts require.
Does a site diary help with the Building Safety Act?
A site diary is not the golden thread, but entries written on the day by named people are dated evidence of what happened on site. On higher-risk buildings, that kind of record can support golden thread information and your Building Safety Act evidence. Take advice on how the duties apply to your projects.
Can entries be written out on site?
Yes. The site diary app works on a phone, so site managers and supervisors can add entries from wherever they are on site, at the time things happen.
Why write diary entries at the time, not at the end of the week?
Entries written as things happen are more accurate, and carry more weight, than notes pieced together from memory. Crate saves each entry with who wrote it and when, so the record shows when it was made.
Works with the rest of Crate
The site diary app sits alongside the other records your site team keeps every day.
Site tours
Site safety inspections on a tablet, scored and rated when submitted.
Site issue register
Log issues from a phone and follow each one through to completion.
Daily activity briefings
Brief the day's tasks, hazards and controls and record who signed.
Permits to work
Issue, approve and accept permits for high-risk work.
Every day on site, written down as it happens.
Book a demo and we'll show you the site diary app in Crate, from the first entry of the morning to the end of day check.