What is a hold point in construction? Hold points and witness points explained

A hold point is a stage in construction where work stops until a named person has inspected it and signed it off. Rebar before the pour. Membranes before they are covered. Firestopping before the boards go on. Miss one and the evidence is under 300mm of concrete, which is a hard place to take a photo.

By G. Wicks, Crate & Wasteify FounderUpdated 20 October 20269 minute read
Site engineer crouching to inspect steel reinforcement in timber formwork with a tablet, beside a Crate confirmation that the quality permit has been approved and sent to the assigned operative

The short answer

  • A hold point is a mandatory stop in the work. The next stage cannot start until the work has been inspected and released in writing by a named person.
  • A witness point is softer. The inspector must be given notice and the chance to attend, but if they do not turn up, work can carry on.
  • Hold points are set in the inspection and test plan for each package of work. A quality permit is the sign-off that records the inspection and releases the work.
Contents
  1. What is a hold point?
  2. Hold and witness points compared
  3. The inspection and test plan
  4. Common hold points
  5. Who signs it off
  6. Does the law require them?
  7. What evidence to keep
  8. How to run hold points
  9. Common mistakes
  10. Paper or digital?
  11. Sources

What is a hold point?

A hold point is a point in the construction sequence beyond which work must not continue until a set inspection, test or approval has taken place. It exists because some work cannot be checked once the next layer goes on. Reinforcement disappears into concrete. Drainage disappears under backfill. Cavity barriers disappear behind cladding.

Hold points come from quality management and the contract, not from an Act of Parliament. They are written into the specification, the subcontract or the inspection and test plan, each with a named person who has the authority to release the work.

Contractors call the sign-off different things: a quality permit, a release, a permit to pour, a permit to cover. Same idea every time. A recorded decision, by someone accountable, that the work is right and the next stage can start.

Hold point, witness point and inspection compared

Most inspection and test plans use three or four types of check. Here is how they usually differ.

TypeWhat it meansCan work carry on without the inspector?Typical example
Hold pointWork stops until the inspection is done and the work is released in writingNoReinforcement checked before a concrete pour
Witness pointThe inspector is given notice and the chance to attend, but work does not have to wait for themYes, once proper notice has been given and the agreed time has passedA drainage air test or a pipework pressure test
Inspection pointThe contractor checks the work as it goes, and keeps the record for reviewYesSetting out, blockwork, fixings and daily checks
Review pointRecords, certificates or test results are reviewed after the eventYesConcrete cube results, material certificates, commissioning records

Names vary between contractors and clients. What matters is that everyone on the package knows which is which before the work starts, not when the concrete wagon is at the gate.

Hold points and the inspection and test plan

An inspection and test plan, or ITP, lists every check for a package of work, in order. It says who checks what, against which standard, and what type of point each check is. It is where hold points live.

ColumnWhat goes in it
ActivityThe stage of work being checked, in the order it happens on site
ReferenceThe drawing, specification clause or standard the work is checked against, with its revision
Acceptance criteriaWhat good looks like, in terms you can measure: cover, laps, falls, fixings, test pressures
Inspection typeHold, witness, inspection or review
ResponsibilityWho checks the work, who witnesses it and who has the authority to release it
RecordThe evidence that proves it was done: a signed quality permit, photos, test certificates

Agree the ITP before the package starts and make sure the people doing the work have seen it. A hold point the operatives do not know about is a note in a file.

Common hold points on construction sites

Every job is different, but the same hold points turn up on most of them. They all have one thing in common: once the next stage starts, the work underneath cannot be seen.

Reinforcement before a pour

  • Bar sizes, spacing and laps against the drawings
  • Cover and spacers
  • Starter bars and cast-in items
  • Formwork clean, sealed and stable

Membranes before cover

  • Laps sealed and taped
  • No tears or punctures
  • Detailing at corners and penetrations
  • Links to the damp-proof course

Firestopping before boarding

  • The right tested system for that service and wall
  • Installed to the manufacturer's details
  • Cavity barriers in place and continuous
  • Labelled and photographed

Drainage before backfill

  • Line, level and falls
  • Bedding and surround
  • Air or water test passed
  • Camera survey where specified

Formation before concrete

  • Formation level and bearing checked
  • Excavation clean and free of water
  • Dimensions and setting out
  • Soft spots dealt with

Services before ceilings close

  • First fix complete and inspected
  • Pipework pressure tested
  • Fire dampers and supports in place
  • Labelling done

Who signs off a hold point?

The ITP or the contract should name them. On most jobs it works like this:

  • The contractor's own engineer or supervisor checks the work first and asks for the inspection
  • The inspector checks it against the drawings and specification. That might be the main contractor's engineer, the designer, a clerk of works or the client's representative
  • The person with the authority to release the work signs it off. Sometimes that is the inspector, sometimes a package or quality manager
  • Building control may also need to inspect some stages, depending on the job and your building control body

Whoever releases the work should have seen it. Since October 2023, the Building Regulations in England have also required anyone carrying out building work to have the "skills, knowledge, experience and behaviours necessary" to do it in line with the regulations (regulation 11F). Signing off work you never saw is a hard thing to defend.

What evidence should a hold point record include?

The record has to stand up long after the work is covered and the people who checked it have moved on. A good one includes:

  • The ITP reference and the exact location: grid line, level, plot or room
  • The drawing and specification revision the work was checked against
  • Photos taken before the work was covered, showing the location and enough detail to prove the point
  • Measurements and test results, such as cover, laps, falls and test pressures
  • Anything that failed, what was done about it and the re-inspection
  • Who inspected the work, who released it and when, with signatures

Keep it with the site records, not on one engineer's phone. People leave jobs. Their camera rolls leave with them.

How to run hold points that work

A hold point is only as good as the discipline around it. Here is what that looks like on site.

  1. Agree them before the package starts

    Set the hold points in the inspection and test plan at the start, and write them into the subcontract. Arguing about whether something was a hold point after the pour helps nobody.

  2. Put them on the programme

    If the inspector needs 24 hours' notice, the programme needs those 24 hours. Hold points that are not planned get skipped when the pressure is on.

  3. Give proper notice

    Tell the inspector what is ready, where and when, with the ITP reference. "It will be ready sometime tomorrow" is not notice.

  4. Inspect against the criteria

    Check the work against the drawing and specification, not against what looks about right.

  5. Record it at the work area

    Photos, measurements and the result, captured where the work is, not written up in the cabin on Friday.

  6. Release it in writing

    Nothing gets covered until the release is signed and the gang doing the next stage knows it has been.

  7. Fix failures and re-inspect

    If it fails, record what was wrong, fix it and inspect it again. A failure with a recorded fix is good evidence. A failure with no record of the fix is a problem waiting to be found.

Common hold point mistakes

Most hold point failures happen under programme pressure, and most are avoidable.

  • The concrete is already bookedA wagon on its way turns a hold point into a formality. Book the pour after the release, or book the inspection early enough to make it real.
  • Photos with no contextA close-up of some rebar could be any slab on any job in the country. Get a wider shot with a grid line, a level or a tape in it.
  • Signing from the cabinApproving a pour from a blurry photo sent at 6.45am is not an inspection. It is a guess.
  • Hold and witness points mixed upTreat a witness point as a hold point and the job stalls. Treat a hold point as a witness point and work gets covered that nobody checked.
  • The gang never saw the planOperatives cannot stop at a hold point they do not know exists.
  • No record of the re-inspectionThe failure is logged, the fix is not, and the record now shows defective work that was covered up.

Paper sign-off sheets or digital quality permits?

Paper hold point sheets live in a folder in the cabin. The photos live on someone's phone. Two years later, when the client asks for evidence of the firestopping on level 6, the folder has gone in a skip and the phone has been upgraded twice.

In Crate, hold points are signed off as quality permits. An engineer or supervisor raises the permit and sends it for approval. Once the work has been inspected, it is approved and sent to the operative assigned to the task. Each permit keeps a dated record of who raised it and who approved it, and operatives sign by QR code, either on the supervisor's screen or on their own phone in the Crate app. Those digital, dated, signed records sit against each site, where they support your golden thread and Building Safety Act evidence.

See how quality permits work in Crate, from raised to approved.Quality permits in Crate

Sources

  1. Building Regulations 2010, Part 2A Dutyholders and competence, legislation.gov.uk
  2. Building Regulations etc. (Amendment) (England) Regulations 2023, legislation.gov.uk
  3. Keeping information about a higher-risk building: the golden thread, GOV.UK
  4. Criteria for determining whether a new building is a higher-risk building, GOV.UK

Hold point questions

The questions site teams ask us most, answered straight.

What is a hold point in construction?

A hold point is a stage in the work where everything stops until the work has been inspected and released by a named person. It is used where the work will be covered up or cannot be checked later, such as reinforcement before a concrete pour.

What is the difference between a hold point and a witness point?

At a hold point, work cannot continue until the inspection is done and the work is released. At a witness point, the inspector is given notice and can attend, but work can carry on if they do not.

What is an inspection and test plan?

An inspection and test plan, or ITP, lists the checks for a package of work in order, with the standard each is checked against, who checks it and whether it is a hold, witness, inspection or review point.

Who can release a hold point?

The person named in the inspection and test plan or the contract, often an engineer, the designer, a clerk of works or the client's representative. They should have inspected the work themselves.

Are hold points a legal requirement?

No law uses the term hold point. In England, the Building Regulations 2010 require anyone carrying out building work to plan, manage and monitor it so that it complies, and hold points are one of the clearest ways to show that.

What is a quality permit?

A quality permit is a written sign-off for a hold point. It records that the work was inspected and approved, and releases the next stage of work.

What evidence should you keep for a hold point?

Keep the location, the drawing revision, photos taken before the work was covered, measurements or test results, any failures and re-inspections, and who inspected and released the work, with dates.

Do hold points matter more on higher-risk buildings?

Yes. On higher-risk buildings the principal contractor must keep evidence that the building work meets building regulations, and hold point records show the work at the moment before it was hidden.