How to keep a construction site diary that stands up later
To keep a construction site diary that stands up later, write it every day, on the day, with facts, numbers and names: who was on site, what got done, what held the job up and what you were told. A diary written like that is often the best evidence you will have in a delay claim or a dispute months down the line. One written up on a Friday from memory is not.

The short answer
- A construction site diary is a daily record of labour, plant, work done, weather, delays, instructions, visitors and incidents on a site, usually kept by the site manager.
- No UK law requires a site diary on every project, but some contracts ask for daily records, and records made at the time are usually the strongest evidence in delay claims and disputes.
- Write it every day, on the day, with specific facts. Keep one diary per site that the business controls, not notes spread across personal phones and WhatsApp groups.
Contents
What is a construction site diary for?
A site diary is the day-by-day story of the job, written while it happens. Most days nobody reads it. Then a client disputes an extension of time, a neighbour says the piling cracked their wall, or someone gets hurt, and the diary is the first thing everyone asks for.
- Delays and extensions of time. What held the work up, when, and which activities it affected.
- Claims and variations. Instructions given on site, extra work, and the labour and plant it took.
- Disputes. Who was on site, what was done and what was said, on the day it happened.
- Incidents. Conditions, who was involved and what happened next, alongside the accident book and any RIDDOR report.
- Visitors and inspections. Clients, building control, HSE inspectors, utilities and anyone else who came through the gate.
The value comes from when it was written. Records made at the time, known as contemporaneous records, carry far more weight than anyone's memory a year later. Lawyers who handle delay claims say it plainly: expert evidence helps, but contemporaneous records are the best evidence you can have.
Is a construction site diary a legal requirement?
No UK law requires a site diary on every project. There is no regulation telling a site manager to write one each night.
Contracts are a different matter. Some contracts and subcontracts ask for daily site records, and many principal contractors require them in their own procedures. Even where the contract says nothing about diaries, notice periods are strict. Under the NEC4 contracts, for example, a contractor who does not notify a compensation event within eight weeks of becoming aware of it can lose the right to more time or money, with some exceptions. You cannot notify what nobody wrote down.
On higher-risk buildings, the Building Safety Act regime adds record-keeping duties for principal contractors. The government's guidance says:
"you must use the record-keeping system provided by the client to ensure that information about the building is up to date"
gov.uk, Keeping information about a higher-risk building: the golden thread
That duty is about the golden thread, not site diaries, and it only applies to higher-risk buildings. How the two connect is covered further down.
This is general guidance, not legal advice. Take advice on how the duties apply to your business and your projects.
Who should keep the site diary?
The site manager owns it. They see the whole job, they deal with the client and the subcontractors, and they are the person who will be asked about it later.
That does not mean they write every word. On bigger jobs, supervisors and section managers add entries for their own areas, and the site manager reads through the day's entries before leaving site.
What matters is one diary per site, owned by the business. Three people each keeping their own notebook gives you three partial records that will disagree with each other on the one day that matters.
Write it before you leave site, while the detail is fresh. With the same headings every day, ten minutes is plenty.
What to record in a construction site diary
If you are wondering what to record in a site diary, start with the same headings every day. Gaps stand out, and entries are easy to compare. These are the ones that matter later.
| Entry | What to write | Why it matters later |
|---|---|---|
| Date and weather | The date, start and finish times, the weather morning and afternoon, and conditions underfoot | Weather delays get argued about constantly. Specifics win. |
| Labour | Numbers on site by company and trade | Shows resources against the programme, and who was really there |
| Plant | What was on site, what was working, and what was stood or broken down | Idle plant costs money, and you will need to show it |
| Work done | What was done and where, by area, level or grid line | Progress against the programme, in your words, on the day |
| Delays and disruption | What held the work up, from when to when, and which activities it affected | The heart of any extension of time claim |
| Instructions | Instructions given on site, by whom, and what they changed | Verbal instructions vanish unless someone writes them down |
| Visitors and inspections | Who came, why, and what they said or found | Client, building control and HSE visits are hard to piece together later |
| Deliveries | What arrived and when, and anything late, short or damaged | Explains lost time and backs up any charges |
| Incidents and near misses | What happened and who was involved, with a reference to the accident book or RIDDOR report | Adds the context those records leave out |
| Photos | Dated photos of progress, conditions and problems, linked to the entry | A photo with no date or context proves very little |
How to write site diary entries that stand up later
A diary is only worth something if it is believed. These habits make the difference.
Write it every day, on the day
Same day, before you leave site. A week written up on a Friday afternoon reads like exactly that, and anyone challenging it will notice.
Stick to facts
Numbers, times, names and places. "Groundworks delayed" is an opinion. "Excavation in area C stopped from 10.15 to 2.30, water ingress, pump hired" is a record.
Say what the delay affected
Name the activity and the area. In one Australian case, the court found the site diaries well kept and clear, but they did not identify which activities were held up waiting for a new sewer design. A good diary, missing the one fact that mattered.
Record what you were told, and by whom
Verbal instructions, warnings and promises. Who said it, when, and what it changed. Then confirm anything important in writing through the proper contract route.
Add photos to the entry
Dated photos attached to the day they belong to. Photos sitting in someone's camera roll are not part of the record until they are.
Never rewrite, add a correction
If an entry is wrong, add a dated note saying what changed and why. An entry quietly edited weeks later loses most of its value.
WhatsApp group, paper diary or a site diary app?
Plenty of sites run their diary on a WhatsApp group. It is quick, everyone already has it, and photos go up in seconds. As a record, it has real problems.
| What matters | Paper diary | WhatsApp group | Site diary app |
|---|---|---|---|
| Who controls the data | Whoever has the book | Nobody centrally. It lives on each member's phone | The business |
| Backups | None. Lose the book, lose the record | Depends on each person's own phone and backup settings | Held centrally, not on one device |
| Who can see it | Whoever has it in their hand | Only people added to the group | Everyone the business gives access to the site |
| When people leave | The book often leaves with them, or ends up in a skip | Their history leaves with them | The record stays with the site |
| Proving who wrote what, and when | Handwriting and trust | Names and times, buried in chat | Each entry saved with who wrote it and when |
| Finding a day from eight months ago | Archive boxes and luck | Scrolling past banter and "running late" messages | Organised by site and date |
WhatsApp is a messaging app, not a record system. Use it to talk. Keep the diary somewhere the business controls.
Common site diary mistakes
Most diaries that fail under scrutiny fail in the same few ways.
- One-word entries"Rain." Which morning, how heavy, what stopped and what carried on? A one-word entry helps nobody.
- Opinions and blame"The groundworker is useless again" could be read out in an adjudication. Write what happened, not what you think of it.
- Gaps on the days that matterDiaries tend to stop exactly when the site gets busy and difficult, which is when they are needed most.
- A personal notebookThe diary in the site manager's pocket leaves when the site manager does. The record belongs to the job.
- Photos with no contextThree hundred photos of mud, with no date, location or note, prove that there was mud.
Site diaries, the golden thread and the Building Safety Act
The golden thread is the digital information about a higher-risk building: at least 18 metres or 7 storeys high with at least 2 residential units, or a hospital or care home. During design and construction, the principal contractor must use the client's record-keeping system to keep that information up to date, keep evidence that the work meets building regulations, and manage change control. The information has to be kept digitally, secure and easy to understand.
A site diary is not the golden thread, and it does not replace it. What it does is support it. A dated entry recording an instruction that changed a detail, an inspection by building control, or who installed what and when, is the kind of evidence that is hard to recreate afterwards.
Even on projects that are not higher-risk buildings, the Building Safety Act's dutyholder and competence duties apply to all building work. Good daily records help show who did what, and when.
Keeping your construction site diary in Crate
Paper diaries leave with people, and WhatsApp groups scatter the record across everyone's phones. Neither gives the business one place to look.
In Crate, diary entries are written on a phone, on site, as the day happens. Each entry is saved with who wrote it and when. There is one diary per site, and everyone with access to the site can see it, so the record stays with the job when people move on.
Sources
Site diary questions
The questions site teams ask us most, answered straight.
What is a construction site diary?
A construction site diary is a dated daily record of what happened on site: labour, plant, work done, weather, delays, instructions, visitors and incidents. It is usually kept by the site manager.
Is a site diary a legal requirement in the UK?
No law requires a site diary on every project. But some contracts ask for daily records, and without them it is much harder to prove delays, claims or what happened in a dispute.
Who should keep the site diary?
The site manager usually owns it, with supervisors adding entries for their areas. Keep one diary per site that the business controls, not a notebook per person.
What should you write in a site diary?
Weather, labour by trade, plant, work done and where, delays and what they affected, instructions received, visitors, deliveries, incidents and dated photos. Facts, times and names, not opinions.
How often should you write in a site diary?
Every working day, on the day. Entries written up days later carry far less weight and miss the detail that matters.
Can a site diary be used as evidence?
Yes. Records made at the time are usually the strongest evidence in delay claims and disputes, and a clear daily diary is one of the main ones.
Is a WhatsApp group a good site diary?
Not on its own. Nobody controls the data centrally, backups depend on each person's own phone, only group members can see it, and history leaves with people when they leave.
Can you change a site diary entry after it is written?
Do not rewrite it. Add a dated correction that says what changed and why, so the original entry and the correction can both be seen.
More on site records
The site diary sits alongside the other records your site teams keep every day.
Site diary
Entries written on site, saved with who wrote them and when.
What is a site issue register?
How to log problems found on site and see them closed out.
What is a daily activity briefing?
The start-of-shift briefing on the day's work.
Hold points in construction
When work stops for an inspection or sign-off before it carries on.
A site diary that stands up when it matters.