Plant guide

LOLER and PUWER inspections explained

LOLER and PUWER are the two sets of regulations that decide how plant and equipment on a UK site must be inspected. PUWER covers all work equipment and asks for inspections at suitable intervals. LOLER covers anything that lifts, and asks for a thorough examination by a competent person at fixed intervals, with a written report. Mix them up and you end up with a folder of service sheets and no certificate when someone asks for one.

By G. Wicks, Crate & Wasteify FounderUpdated 20 October 202610 minute read
Excavator, forklift and site equipment inspected in Crate with defects graded safe or not safe to use

The short answer

  • PUWER 1998 covers all work equipment, from a disc cutter to a dumper. Equipment that can deteriorate must be inspected by a competent person at suitable intervals, and the result recorded.
  • LOLER 1998 covers lifting equipment such as cranes, forklifts, MEWPs, hoists, slings and chains. It needs a thorough examination by a competent person at least every 6 months for lifting accessories and anything that lifts people, and every 12 months for other lifting equipment, unless an examination scheme says otherwise.
  • Every thorough examination ends in a written report. Dangerous defects take the equipment out of use, and where there is an existing or imminent risk of serious personal injury the examiner sends a copy to the enforcing authority.
Contents
  1. What do LOLER and PUWER cover?
  2. What the law requires
  3. Thorough examination intervals
  4. Who is a competent person?
  5. Reports and defects
  6. Checks, inspections and examinations
  7. Hired-in plant
  8. Setting up an inspection regime
  9. Common failures
  10. Paper or digital?
  11. Sources

What do LOLER and PUWER cover?

PUWER is the Provision and Use of Work Equipment Regulations 1998. It covers "any machinery, appliance, apparatus, tool or installation for use at work". On a building site, that is nearly everything: the disc cutter, the breaker, the mixer, the dumper, the excavator, the generator. PUWER says equipment must be suitable for the job, maintained, inspected where needed, and used only by people trained to use it.

LOLER is the Lifting Operations and Lifting Equipment Regulations 1998. It covers lifting equipment, defined as "work equipment for lifting or lowering loads", and lifting accessories such as slings, chains, shackles and eyebolts. A person counts as a load, so MEWPs and hoists that carry people are in.

LOLER does not replace PUWER. It sits on top of it. A forklift is work equipment under PUWER, so it needs maintaining, a trained operator and daily pre-use checks. It is also lifting equipment under LOLER, so its chains, forks and mast need thorough examination and its lifts need planning.

Some things people assume are lifting equipment usually are not. HSE says pallets and skips carrying materials are not normally lifting equipment. The chains used to lift the skip are.

What do LOLER and PUWER require?

PUWER regulation 6 deals with inspection. Where equipment is exposed to conditions that cause deterioration liable to result in dangerous situations, it must be inspected "at suitable intervals" and each time something exceptional happens that could affect its safety. Equipment whose safety depends on how it was installed must also be inspected after installation and before first use. The regulations define an inspection as "such visual or more rigorous inspection by a competent person as is appropriate for the purpose". There is no fixed interval. You set it, based on risk.

LOLER regulation 9 is far more specific. Lifting equipment exposed to conditions that cause deterioration must be thoroughly examined:

"(i) in the case of lifting equipment for lifting persons or an accessory for lifting, at least every 6 months; (ii) in the case of other lifting equipment, at least every 12 months; or (iii) in either case, in accordance with an examination scheme"

Lifting Operations and Lifting Equipment Regulations 1998, regulation 9(3)(a)

It must also be examined each time exceptional circumstances could have affected its safety and, where appropriate, inspected by a competent person between examinations.

In plain English: PUWER makes you work out how often your kit needs looking at, then prove you did it. LOLER sets the maximum gap between thorough examinations and wants a written report every time. If it lifts, both apply.

This is general guidance, not legal advice. Take advice on how the duties apply to your business and your projects.

LOLER thorough examination intervals

A LOLER thorough examination is a detailed, systematic check of lifting equipment and its safety-critical parts by a competent person. It can include functional checks, wear measurements and, where the risk calls for it, testing.

Equipment or eventMaximum intervalSite examples
Equipment for lifting peopleAt least every 6 monthsMEWPs, mast climbing work platforms, hoists that carry people
Lifting accessoriesAt least every 6 monthsSlings, chains, shackles, hooks, eyebolts, lifting beams
Other lifting equipmentAt least every 12 monthsCranes, forklifts, telehandlers, goods hoists, excavators used for lifting
Under an examination schemeAs the scheme setsIntervals set by a competent person, shorter or in some cases longer than the fixed ones
Before first useBefore it goes into serviceNot needed for new kit with a declaration of conformity less than 12 months old that was not assembled on site
After installation or assemblyAt each new location, before useTower cranes and anything else whose safety depends on how it is put up
After exceptional circumstancesEach time they happenDamage, an accident, long periods out of use, major changes

Examination schemes

An examination scheme is the alternative to the fixed intervals. A competent person draws it up, setting out which parts are examined, how, and how often. It can tighten the intervals for kit that works hard, or stretch them where the equipment's history supports it. It does not have to be a paper document, but you must be able to produce a written copy when asked.

Who counts as a competent person?

Neither set of regulations defines it. For LOLER, HSE guidance describes someone with "such appropriate practical and theoretical knowledge and experience" of the equipment to spot defects and judge how serious they are.

They must also be independent and impartial enough to make objective decisions. They can be employed by you, but they should not be the person who services the machine. Nobody should be examining their own work. In practice, many firms use an engineer from a specialist inspection company or an insurer.

PUWER inspections are less formal. HSE says they can be done by "anyone who has sufficient knowledge and experience of it", often someone in-house, as long as they know what to look at, what to look for and what to do when they find a problem.

What must a report of thorough examination contain?

LOLER Schedule 1 lists what goes in the report. There is no set form, but every report needs:

  • The employer, the address where the examination was made, and enough detail to identify the equipment
  • The date of the last thorough examination and the safe working load
  • What kind of examination it was: first after installation, 6 months, 12 months, examination scheme or exceptional circumstances
  • A statement that the equipment would be safe to operate, if that is the case
  • Any defect that is or could become a danger to persons, the repair needed, and for a defect not yet dangerous, the time by which it could become so
  • The latest date for the next thorough examination and details of any test
  • The examiner's name, address and qualifications, who employs them, and the dates of the examination and report

When defects must be reported

The examiner must tell you "forthwith" about any defect that is or could become a danger to persons, then send the written report as soon as practicable, to you and to any company the equipment is hired or leased from. If the defect is serious, the enforcing authority hears about it too:

"where there is in his opinion a defect in the lifting equipment involving an existing or imminent risk of serious personal injury send a copy of the report as soon as is practicable to the relevant enforcing authority."

Lifting Operations and Lifting Equipment Regulations 1998, regulation 10(1)(c)

Once you have been told about a dangerous defect, the equipment must not be used until it is fixed (regulation 10(3)). For a defect that could become dangerous later, the report gives a time, and the repair has to be done before then.

Pre-use checks, inspections and thorough examinations compared

Three different jobs that regularly get confused. Here is how they differ.

CheckWho does itWhenWhat it involves
Pre-use checkThe operator or userBefore use, often dailyQuick visual and function checks: tyres, lights, brakes, guards, cables, slings. HSE says the simplest checks do not normally need a record, but most sites ask for one.
PUWER inspectionA competent person, often in-houseAt intervals set by risk, after installation and after anything that could affect safetyA planned inspection of the parts that deteriorate. The result is recorded and kept until the next inspection is recorded.
LOLER inspectionA competent person, often the operator or fitterBetween thorough examinations, where risk assessment says it is neededWeekly or monthly checks on cranes and other lifting equipment. Recorded and kept until the next one.
Thorough examinationA competent person who is independent and impartialEvery 6 or 12 months, or under an examination scheme, plus first use and exceptional circumstancesA detailed examination of lifting equipment and its safety-critical parts, ending in a written report.

Lifting accessories do not normally need formal inspections between examinations, provided they get proper pre-use checks.

LOLER and PUWER for hired-in plant

Hired plant is where the paperwork goes missing. The hire company usually arranges the thorough examination, but HSE is clear that the legal responsibility sits with the user, who should "always satisfy themselves at the outset that there is a current report".

Both sets of regulations back this up. LOLER regulation 9(4) says lifting equipment from another business must not be used unless it is "accompanied by physical evidence that the last thorough examination required to be carried out under this regulation has been carried out". PUWER regulation 6(4) says the same about inspections. When hired plant arrives, check:

  • The current thorough examination report for the machine and every accessory that comes with it
  • The date the next examination is due, against how long you have it on hire
  • Evidence of the last inspection for anything that needs one under PUWER
  • Who is doing the daily pre-use checks, and where they are recorded
  • How defects get reported back to the hire company, and who to call

Check it at the gate, not after the first lift.

How to set up a plant inspection regime

  1. List every item of plant and equipment

    You cannot inspect what you do not know you have. Include hired-in plant, small tools and every sling, chain and shackle.

  2. Decide which rules apply

    LOLER for anything that lifts, PUWER for the rest. Scaffolds and other work at height equipment, excavations and cofferdams have their own inspection rules under the Work at Height Regulations 2005 and CDM 2015.

  3. Set the intervals

    Statutory maximums for LOLER, risk-based intervals for PUWER. Start from the manufacturer's recommendations and shorten them for kit that lives outside in the muck.

  4. Give operators a pre-use check

    Short, specific to the machine and done before use. A generic sheet that covers everything checks nothing.

  5. Book examinations before they fall due

    An out-of-date certificate on a crane stops the job. Know what is due next month.

  6. Deal with defects properly

    Grade them. Take dangerous kit out of use and tag it. Bring it back only when the repair is done and signed off by someone with the authority to do it.

  7. Keep records you can find

    Keep PUWER inspection results until the next one is recorded, and LOLER periodic reports until the next report or for two years, whichever is later. HSE accepts electronic records that cannot be tampered with, as long as you can produce a written copy.

Common LOLER and PUWER failures

The same handful of problems turn up again and again.

  • Treating a service as a thorough examinationHSE is clear that regular servicing does not replace a LOLER thorough examination. Different job, and it should be a different person.
  • The fitter examining his own workThe examiner must be independent and impartial. Signing off the machine you repaired yesterday is neither.
  • Forgetting the accessoriesThe crane has a current certificate. The chains in the back of the van ran out in March.
  • Using it anyway because the job is behindOnce a defect is reported as a danger, the equipment stays out of use until it is fixed. A tight programme does not change that.
  • Lifting with an excavator that is not set up for itHSE says an excavator used for lifting needs the manufacturer's approval, dedicated lifting points with safe working load markings and a thorough examination. Over one tonne lifting capacity, it also needs a rated capacity indicator and boom check valves.
  • Pre-use checks filled in from memoryA sheet ticked on Friday for the whole week records one thing: the day it was ticked.

Paper certificates or a digital plant register?

Paper works until the certificate you need is in a filing cabinet forty miles away. On site, the questions are simple. Is this machine safe to use today, and can you prove it?

Crate is built to help prove inspections under PUWER and LOLER. You build inspection checklists for any asset type, and a QR code or NFC tag on the machine opens the right one. Defects are graded safe or not safe to use, then go to the workshop as tasks, and a defect is cleared only by an authorised close-out with a comment, photo, signature and timestamp. Certificates and key dates, including for hired-in plant, are on your phone, and inspection regimes run on routine intervals. Nothing is deleted, so every asset keeps its full history, manuals and photos.

See how plant and asset inspections work in Crate, from the QR code to the close-out.Plant inspections in Crate

Sources

  1. Lifting Operations and Lifting Equipment Regulations 1998, regulation 9, legislation.gov.uk
  2. Lifting Operations and Lifting Equipment Regulations 1998, regulations 10 and 11, legislation.gov.uk
  3. Lifting Operations and Lifting Equipment Regulations 1998, Schedule 1, legislation.gov.uk
  4. Lifting Operations and Lifting Equipment Regulations 1998, regulation 2, legislation.gov.uk
  5. Provision and Use of Work Equipment Regulations 1998, legislation.gov.uk
  6. Thorough examinations and inspections of lifting equipment, HSE
  7. Inspection of work equipment, HSE
  8. Lifting equipment frequently asked questions, HSE

LOLER and PUWER questions

The questions site and plant teams ask us most, answered straight.

What is the difference between LOLER and PUWER?

PUWER covers all equipment used at work and requires it to be suitable, maintained, inspected where needed and used by trained people. LOLER adds extra rules for lifting equipment, including thorough examinations at fixed intervals and written reports.

How often is a LOLER thorough examination needed?

At least every 6 months for lifting accessories and equipment that lifts people, and at least every 12 months for other lifting equipment, unless an examination scheme sets different intervals. It is also needed before first use, after assembly at a new location and after exceptional circumstances such as damage.

How often should PUWER inspections be done?

PUWER does not set a fixed interval. Equipment that can deteriorate must be inspected at suitable intervals, based on risk, the manufacturer's recommendations and how hard it works, and after anything that could affect its safety.

Who can carry out a LOLER thorough examination?

A competent person with the practical and theoretical knowledge and experience to find defects and judge how serious they are. They must be independent and impartial, so they should not be the person who maintains the equipment.

Is a forklift covered by LOLER or PUWER?

Both. HSE says the lifting parts of a forklift, such as the chains, forks and mast, need a thorough examination every 12 months or under a written scheme, while PUWER requires maintenance and daily pre-use checks.

Do pre-use checks need to be written down?

HSE says records are not normally required for the simplest pre-use checks. Many principal contractors ask for a signed check anyway, and a record is the easiest way to show it happened.

Who is responsible for LOLER on hired plant?

The user. The hire company usually arranges the thorough examination, but you must check there is a current report before the equipment is used.

When must a defect be reported to the enforcing authority?

When the examiner finds a defect involving an existing or imminent risk of serious personal injury, they must send a copy of the report to the enforcing authority as soon as practicable. The equipment must not be used until the defect is fixed.

Every machine inspected. Every defect closed out.

Book a demo and we'll show you plant and asset inspections in Crate, from the QR code on the machine to the signed close-out, using your own equipment.

Book a demo