How to carry out a site safety inspection
To carry out a site safety inspection, walk the whole site with a checklist, check the work against the RAMS and the law, talk to the people doing it, and turn every problem into an action with an owner and a due date. Then follow those actions until they are closed. The walk is the easy part. The follow-up is where most inspections quietly die.

The short answer
- A site safety inspection is a planned check of a construction site against a checklist, covering work at height, excavations, plant, housekeeping, fire, health risks and welfare, with every problem recorded as an action.
- CDM 2015 requires contractors to plan, manage and monitor their work. The law also sets specific inspections: working platforms within the previous 7 days, and supported excavations at the start of every shift.
- A good inspection ends with every problem assigned to one person with a due date, and is followed up until each action is closed.
Contents
What is a site safety inspection?
A site safety inspection is a structured walk around the site to check that work is being done safely and that what the RAMS and the construction phase plan say is actually happening. It uses a checklist, it records what was found, and it creates actions for anything that needs fixing.
Most sites run several. The site manager's daily walk round. A fuller weekly inspection. A monthly visit from the health and safety advisor. And statutory inspections of scaffolds and excavations by a competent person. They do different jobs, and they all need recording.
You will hear them called site safety tours, site walks, safety audits and inspections, often by the same person in the same week. The table further down sorts out which is which.
What does the law say about site safety inspections?
No regulation tells you to hold a weekly site safety inspection. But the duty to monitor construction work is written into CDM 2015, and you cannot monitor a site without going and looking at it.
"The principal contractor must plan, manage and monitor the construction phase and coordinate matters relating to health and safety during the construction phase to ensure that, so far as is reasonably practicable, construction work is carried out without risks to health or safety."
Construction (Design and Management) Regulations 2015, regulation 13(1)
Regulation 15(2) puts the same duty on every contractor for their own work: a contractor "must plan, manage and monitor construction work carried out either by the contractor or by workers under the contractor's control". An inspection is how you monitor. The record is how you prove you did.
Scaffolds and other working platforms
The Work at Height Regulations 2005 set a specific regime. A working platform used for construction work, from which a person could fall 2 metres or more:
"is not used in any position unless it has been inspected in that position or, in the case of a mobile working platform, inspected on the site, within the previous 7 days."
Work at Height Regulations 2005, regulation 12(4)
Regulation 12 also requires inspection after assembly and after exceptional circumstances that could affect safety, such as severe weather. The person who inspects a platform must prepare a report with the details in Schedule 7, and provide it within 24 hours of completing the inspection.
Excavations
Under CDM 2015 regulation 22(4), work must not be carried out in an excavation where supports or battering have been provided unless a competent person has inspected it:
"at the start of the shift in which the work is to be carried out"
"after any event likely to have affected the strength or stability of the excavation"
"after any material unintentionally falls or is dislodged"
Construction (Design and Management) Regulations 2015, regulation 22(4)(a)
If the competent person is not satisfied the work can be done safely, regulation 24 requires them to tell whoever the inspection was carried out for before the end of the shift, and to provide a written report within 24 hours.
Your weekly site safety inspection is not the statutory scaffold or excavation inspection, unless the person doing it is competent for that work and records it properly. It should still check those inspections are current, and that the tag matches what the scaffold actually looks like today.
This is general guidance, not legal advice. Take advice on how the duties apply to your business and your projects.
Site safety inspection, audit and tour compared
The names get swapped around, but these are different jobs.
| Type | What it checks | Who usually does it | How often |
|---|---|---|---|
| Site safety inspection | Physical conditions and how work is being done on the day | Site manager, supervisor or health and safety advisor | A daily walk round, plus a fuller weekly inspection on most sites |
| Statutory inspection | A specific item the law says must be inspected, such as a scaffold or a supported excavation | A competent person for that equipment or work | Set by the regulations, such as within the previous 7 days for working platforms |
| Audit | Whether the system works: training, RAMS, permits, procedures and records | A health and safety advisor or someone independent of the site | Monthly or quarterly, depending on the company |
| Leadership tour | Visible commitment, conversations with the workforce, and the things people on site have stopped noticing | Directors and senior managers | Monthly, or as the company sets |
Frequencies are typical, not legal minimums, except where the regulations set them.
What to check on a site safety inspection
Start with what kills and injures people on construction sites, then work down. A construction site inspection checklist usually covers these areas.
Construction workers killed in Great Britain in 2025/26, compared with an annual average of 37 over the last five years. Falls from height caused around a quarter of all worker deaths.
HSE, Work-related fatal injuries in Great Britain, 2025/26 (provisional)| Area | What to look at |
|---|---|
| Access and housekeeping | Clear walkways, safe access to every work area, materials stored properly, waste under control, enough lighting |
| Work at height | Scaffold inspected and tagged, edge protection complete, openings covered and marked, ladders in good order and used correctly, towers and MEWPs set up properly |
| Excavations | Support or battering in place, edge protection, safe access, spoil and plant kept back from the edge, inspection record current |
| Plant and vehicles | People and plant kept apart, banksmen where needed, pre-use checks done, seat belts worn, keys controlled |
| Lifting operations | Lift plan in place, accessories inspected, exclusion zones set up and respected |
| Electrical | Temporary supplies protected, cables routed safely, 110V tools on site, buried and overhead services identified |
| Fire | Fire points stocked, escape routes clear, hot works under permit, flammables stored safely |
| Health | Dust controls on cutting, noise and vibration controls, face-fit tested masks, COSHH controls in use |
| Welfare | Toilets, washing, drying and rest areas clean and stocked, drinking water available |
| Environment | Spill kits, fuel storage, drains protected, dust, noise and mud kept off neighbours and the road |
| Paperwork at the work face | RAMS briefed and signed, permits in place and on display, operatives inducted |
How to carry out a site safety inspection
Two people can use the same checklist on the same site and come back with very different results. How you walk the site decides whether the inspection finds anything.
Know what you should see
Before you set off, check what work is planned today, which permits are live and what the RAMS say. Then you know what good looks like.
Use a checklist, but look past it
A checklist makes sure the basics get covered every time. It will not spot the thing nobody thought to put on it. Treat it as the minimum.
Go where the work is
Walk the whole site, including the bits nobody likes: the back of the compound, the top lift, the plant room. Problems collect where people do not go.
Talk to the people doing the work
Ask operatives what they are doing, how, and what would make it safer. Five minutes of conversation tells you more than an hour of looking.
Record as you go
Mark each item as you check it and photograph anything wrong. Notes written up in the cabin afterwards lose detail, and sometimes lose whole items.
Deal with danger on the spot
If something is dangerous, stop the work and make it safe there and then. Do not log it and walk on.
Raise actions with owners and dates
Every problem leaves the inspection with one named owner and a realistic due date.
Close the loop
Follow actions up until they are closed and tell the site team what you found. The next inspection starts by checking the last one's actions.
Rating and scoring an inspection
Many contractors score their inspections. Done well, a score lets you compare sites, follow one site over time and spot standards slipping before something happens.
Most scoring works on the same idea. Each question is marked compliant, non-compliant or not applicable, and the score reflects how many of the applicable questions passed. Some systems weight questions, so missing edge protection costs more than an overflowing bin. The score is then turned into a rating, such as good, fair or poor.
Three rules keep scores honest:
- Not applicable means not applicable. Marking questions N/A to lift the score fools nobody for long.
- A high score with one serious finding is still a bad day. Immediate danger matters more than the number.
- Compare like with like. Groundworks in February and a fit-out in July will not score the same, and should not be judged the same.
A score falling over a few weeks is one of the best early warnings a site will give you.
Raising and closing actions
An inspection is only as good as what happens afterwards. Every non-compliant answer needs an action, and every action needs:
- A clear description and location, with a photo
- One owner, by name or company
- A due date that matches the risk
- A close-out, with a photo of the fix and who checked it
Review open actions at the start of every inspection. If the same action has been open for three weeks, the problem is not the handrail. Problems found outside an inspection belong in your site issue register, tracked the same way.
Health and safety, environmental and leadership tours
Most contractors run more than one kind of site safety tour. They share a method but look for different things.
Health and safety tour
- Work at height and edge protection
- Excavations, plant and vehicles
- Fire, electrics and housekeeping
- RAMS and permits at the work face
Environmental tour
- Spill kits and fuel storage
- Drains and watercourses protected
- Waste segregation and skips
- Dust, noise and mud on the road
Leadership tour
- Conversations with operatives
- What gets in the way of working safely
- Welfare and morale
- Follow-up on concerns raised last time
Themed inspection
- Fire safety walk
- Temporary works
- Dust, noise and other health risks
- Plant and lifting operations
Leadership tours are not meant to catch people out. A director ticking boxes looks like an audit to the workforce. A director who stops and asks questions hears things the site manager never does.
Common site safety inspection mistakes
Most weak inspections fail in the same few ways.
- The same route every timeYou see the same things and miss the same things. Change the route and the time of day.
- Ticking from the cabinIf you did not see it, you did not check it.
- Problems found, never fixedAn inspection that finds twelve problems and fixes none of them is a guided tour.
- Looking but never askingThe operatives know exactly where the shortcuts are. Ask them.
- Scores that only go upEither the site is perfect or the questions are too easy. It is rarely the first one.
- Treating it as the scaffold inspectionYour walk round should check the scaffold inspection is current. It does not replace it.
Paper checklists or digital site safety inspections?
Paper checklists get filled in, signed and filed. Then the actions on them get forgotten, because nobody is going to dig through a lever arch file to see what is still open.
In Crate, site safety tours are done on a tablet or phone. Each question is marked as you walk, and an action can be created from any non-compliant answer on the spot. When the tour is submitted, it gets an overall score and rating. Templates cover health and safety, environmental and leadership tours, so each type of inspection asks the right questions.
Sources
- Construction (Design and Management) Regulations 2015, regulations 13, 15, 22 and 24, legislation.gov.uk
- Work at Height Regulations 2005, regulation 12, legislation.gov.uk
- Work-related fatal injuries in Great Britain, 2025/26, HSE
Site safety inspection questions
The questions site teams ask us most, answered straight.
What is a site safety inspection?
A site safety inspection is a planned walk around a construction site, using a checklist, to check that work is being done safely and that controls are in place. Anything wrong is recorded as an action with an owner and a due date.
How often should a site safety inspection be carried out?
Most UK sites do a daily walk round and a fuller weekly inspection, with regular visits from a health and safety advisor. No law sets a general frequency, but working platforms someone could fall 2 metres or more from must have been inspected within the previous 7 days, and supported excavations at the start of each shift.
Who can carry out a site safety inspection?
Anyone competent to recognise the hazards on that site, usually the site manager, a supervisor or a health and safety advisor. Statutory inspections of scaffolds and excavations must be done by a competent person for that work.
What is the difference between a site inspection and an audit?
An inspection checks physical conditions and how work is being done on the day. An audit checks whether the management system works, such as training, RAMS, permits and records.
What should a construction site inspection checklist include?
Access and housekeeping, work at height, excavations, plant and vehicles, lifting, electrics, fire, health risks such as dust and noise, welfare, environmental controls, and whether RAMS and permits are in place at the work face.
Is a site safety inspection a legal requirement?
CDM 2015 requires principal contractors and contractors to plan, manage and monitor construction work, and regular inspection is the usual way to monitor. Specific inspections of working platforms and supported excavations are required by law.
What is a leadership safety tour?
A leadership tour is a site visit by directors or senior managers, focused on talking to the workforce and showing that safety matters to the people at the top, rather than ticking a checklist.
Should site safety inspections be scored?
Scoring helps compare sites and spot falling standards over time, as long as nobody games it. A serious finding should always matter more than the overall score.
Inspect and follow up in Crate
Site safety tours sit alongside the issues, permits and inspections for the same site.
Site safety tours
Checklists on a tablet or phone, actions on the spot and a score at the end.
What is a site issue register?
Logging problems on site and closing them out.
Plant inspections
Inspection checklists for any asset, with defects graded safe or not safe to use.
What is a permit to work?
HSG250, roles and the permit process, explained for construction.
Inspections that end with actions closed.
Book a demo and we'll show you site safety tours in Crate, from checklist to score and actions, using your own sites.