What is a daily activity briefing (DAB)? A guide for construction sites
A daily activity briefing is a short briefing at the start of each shift where the supervisor tells the team what is happening on site today, what could hurt them and how it is being controlled. Five to ten minutes, every day, before the tools come out. It is the one briefing that should be different every morning. When it isn't, nobody is listening.

The short answer
- A daily activity briefing (DAB) is a short briefing at the start of each shift covering the day's work, the hazards, the controls and anything that has changed since yesterday.
- No UK law uses the words daily activity briefing. But employers must give workers the information, instruction and supervision they need, and principal contractors must consult workers in good time. A DAB does both, every day.
- Keep it to five to ten minutes, give it before work starts, and keep a signed record of who was briefed.
Contents
What is a daily activity briefing?
A daily activity briefing, usually shortened to DAB, is the start-of-shift briefing where a supervisor or site manager runs through the day ahead. What is being done, where and by whom. What could hurt people and what is in place to stop it. Who else is working nearby. What is turning up on the back of a wagon at ten o'clock.
Some contractors call it a daily briefing, a pre-start briefing or the morning brief. The name matters less than the content. It is about today, on this site, for these people.
The difference between a DAB and most other paperwork on site is that it goes out of date every 24 hours. That is the point of it. The RAMS tell you how the job should be done. The DAB tells you what the site looks like this morning.
Daily activity briefings compared with other site briefings
On a busy site the briefings start to blur, and the names get used loosely. This is how they usually split.
| Briefing | When | What it covers | How long |
|---|---|---|---|
| Daily activity briefing | At the start of every shift | Today's work, hazards, controls, interfaces, deliveries, permits, weather and changes since yesterday | Five to ten minutes |
| Toolbox talk | Regularly, often weekly | One health and safety topic in more depth | Ten to fifteen minutes |
| RAMS briefing | Before a task starts, and again when the RAMS change | The agreed method, risks and controls for one task | As long as the task needs |
| Point of work briefing | At the work area, just before the task starts | Final checks that the task, the area and the team still match the plan | A few minutes |
They work as a set. A DAB does not replace the RAMS briefing, and a toolbox talk does not replace either. If your DAB regularly runs to 25 minutes, it is probably trying to be all three.
What should a daily activity briefing cover?
Every site is different, but a good DAB covers the same ground each morning. Use this as a running order and skip what genuinely does not apply today.
Today's work
- What each gang is doing
- Where, by area, level or grid
- Who is supervising each task
- Hold points and inspections due
Hazards and controls
- The main risks of today's tasks
- The RAMS controls that matter today
- Exclusion zones and barriers
- PPE beyond the site minimum
Interfaces between trades
- Who is working above or below whom
- Shared access, hoists and scaffolds
- Areas handed over or closed off
- Noisy or dusty work near others
Deliveries and plant
- Deliveries due and when
- Crane lifts and lift plans
- Plant movements and traffic routes
- Unloading areas and banksmen
Live permits
- Hot works
- Excavations and breaking ground
- Confined spaces
- Electrical isolations
Weather
- Wind and crane limits
- Rain, ice and slippery surfaces
- Heat, sun and drinking water
- Cold, daylight and lighting
Emergency arrangements
- Fire points and assembly point
- First aiders on site today
- Rescue plans for today's tasks
- Changes to escape routes
Changes since yesterday
- Near misses and incidents
- Safety alerts and new site rules
- Areas now open or closed
- Actions from yesterday's briefing
Who gives the briefing, and how long should it take?
The person who runs the work gives the DAB. Usually that is the supervisor, foreman or site manager, because they know what is happening today and can answer the questions that come back.
On bigger sites it often runs in two stages. The principal contractor holds a short coordination meeting with each subcontractor's supervisor, where the clashes get sorted: two trades wanting the same hoist, a crane lift over an area another gang is working in. Each supervisor then briefs their own gang. The second briefing is the one the operative hears, so the detail has to survive the walk from the cabin.
Five to ten minutes is about right. Long enough to cover the day properly and take questions. If it is the same length every day regardless of what is happening, it is being read, not given.
Give it before work starts. A briefing at ten o'clock about work that started at half seven is a record, not a briefing.
Is a daily activity briefing a legal requirement?
No UK law uses the words daily activity briefing, and nothing says you must gather the gang at half seven every morning. What the law does require is that people know the risks of the work in front of them and what is being done about them.
"the provision of such information, instruction, training and supervision as is necessary to ensure, so far as is reasonably practicable, the health and safety at work of his employees"
Health and Safety at Work etc. Act 1974, section 2(2)(c)
The Management of Health and Safety at Work Regulations 1999 add detail. Regulation 10 says employers must give employees "comprehensible and relevant information" on the risks to their health and safety "identified by the assessment" and on "the preventive and protective measures". On a construction site the risks change daily, so the information has to keep up.
The Construction (Design and Management) Regulations 2015 put a specific duty on the principal contractor to:
"consult those workers or their representatives in good time on matters connected with the project which may affect their health, safety or welfare"
Construction (Design and Management) Regulations 2015, regulation 14(b)
In good time means before the work, not after the near miss. CDM also requires the principal contractor to plan, manage, monitor and coordinate the construction phase (regulation 13), and the interfaces between trades are where coordination most often breaks down. A DAB that covers who is working where is that coordination reaching the people on the tools.
So the law does not make you hold a DAB. It makes you inform, instruct, supervise, coordinate and consult, every day the work changes. A daily briefing with a signed record is the simplest way to do that and show you did.
This is general guidance, not legal advice. Take advice on how the duties apply to your business and your projects.
How to run a daily activity briefing
Everyone has stood through the version where the supervisor reads a sheet aloud and a pen goes round. Here is the other version.
Prepare it the afternoon before
Look at tomorrow's programme, deliveries, permits and the forecast before you leave site. Use a daily activity briefing template for the running order, then fill it with what is actually happening. Writing the DAB at 7.25 usually means writing yesterday's again.
Hold it where people can hear
Out of the wind, away from running plant, with a site plan or drawing to point at. Same time every day, so nobody has an excuse to miss it.
Lead with what has changed
New hazards, closed areas, yesterday's near miss, today's crane lift. Start with the news, not the boilerplate everyone has heard forty times.
Be specific
Not "watch out for plant movements". Say the 13 tonne excavator is working in the north car park from ten, and the walkway there is shut until two.
Ask questions and check understanding
Ask someone where the exclusion zone is for the lift, or where the assembly point is while the main one is shut. A row of nods tells you nothing, especially when English is not everyone's first language.
Get it signed, and rebrief when the plan changes
Everyone briefed signs, including late arrivals. If the plan changes at eleven, because the crane is stood down or the wind picks up, gather people again. The morning briefing covers the morning plan.
What should a DAB record include?
When something goes wrong at two in the afternoon, the first question is what people were told that morning. The record answers it. Include:
- The date, site and time of the briefing
- Who gave it
- The work, hazards and controls covered
- Live permits and any attachments referred to, such as a lift plan or traffic management plan
- Who was briefed, each with a signature, and who was missing
- Questions raised and actions agreed, with who owns each one
- Any rebrief later in the day, and who attended it
Keep the briefing and the signatures together. A sheet of signatures with no record of what was said proves that people were standing near a cabin.
Common daily activity briefing mistakes
Most DABs that fail, fail in the same few ways.
- Copying yesterday's briefingIf today's sheet matches yesterday's apart from the date, one of them is fiction.
- Generic hazardsSlips, trips and falls, every day for six months, is wallpaper. The real hazard of the day gets lost behind it.
- Reading the RAMS aloudThe DAB points to the controls that matter today. Reading out twelve pages of method statement is how you lose the room.
- Missing the late arrivalsThe gang briefed at half seven is not the whole site by nine. Agency staff and visiting trades need the same briefing, not a nod towards the cabin.
- No follow-upIf someone flags a missing barrier on Monday and it is still missing on Wednesday, they will not bother flagging the next one.
Paper or digital daily activity briefings?
Paper DABs work on a small site with one gang. Past that, the cracks show. Sheets get filled in after the event, attachments live in someone's inbox, and nobody can tell you at a glance who on site has not been briefed today.
In Crate, supervisors build each day's briefing from their site's templates, with custom fields and attachments such as a lift plan, a drawing or photos. Operatives sign by QR code in one of two ways. The supervisor scans each operative's passport QR code and they sign on the supervisor's screen, or operatives scan the briefing's QR code and sign on their own phone in the Crate app. Less queuing at the cabin door. The supervisor sees who has signed and who has not.
Operatives can open the briefing on their own phone, translated into their own language, and read along as it is delivered. Records are kept by site and date, signed briefings show in each operative's passport, and every briefing has a PDF record.
Sources
- Health and Safety at Work etc. Act 1974, section 2, legislation.gov.uk
- Management of Health and Safety at Work Regulations 1999, legislation.gov.uk
- Construction (Design and Management) Regulations 2015, regulation 14, legislation.gov.uk
- Construction (Design and Management) Regulations 2015, regulation 13, legislation.gov.uk
Daily activity briefing questions
The questions site teams ask us most, answered straight.
What is a daily activity briefing?
A daily activity briefing is a short briefing at the start of each shift where a supervisor or site manager runs through the day's work, the hazards, the controls and anything that has changed since yesterday. It usually takes five to ten minutes.
What does DAB stand for in construction?
DAB stands for daily activity briefing. Some contractors call it a daily briefing, a pre-start briefing or the morning brief.
Is a daily activity briefing a legal requirement?
No UK law uses the term. But employers must give workers the information, instruction and supervision they need, and principal contractors must consult workers in good time on matters that affect their health and safety. A daily briefing is a common way to do both and to show you have.
How long should a daily activity briefing take?
Five to ten minutes is about right. Long enough to cover the day and take questions, short enough that people are still listening at the end.
Who should give the daily activity briefing?
The supervisor, foreman or site manager running the work, because they know what is happening today and can answer questions. On larger sites the principal contractor often coordinates first, then each subcontractor supervisor briefs their own gang.
What is the difference between a DAB and a toolbox talk?
A DAB covers today's work, hazards and controls at the start of every shift. A toolbox talk goes deeper into one health and safety topic, usually once a week.
Do operatives need to sign a daily activity briefing?
No law requires a signature, but a signed record is the usual evidence of who was briefed and on what. Keep the signatures with the content of the briefing, not on a separate sheet.
What if someone arrives after the briefing?
Brief them before they start work. Someone who missed the DAB does not know today's hazards, permits or who is working around them.
More on site briefings
Daily briefings sit alongside the other briefings your site teams give every week.
Daily activity briefings
Site templates, QR sign-in and a signed record every day.
What is a toolbox talk?
How to run a weekly safety talk people actually listen to.
What is a point of work briefing?
Final checks at the work area, right before the task.