What is a permit to work? HSG250 explained for construction

A permit to work is a formal written system for controlling high-risk jobs such as hot works, confined space entry and electrical isolation. It sets out exactly what work will be done, where, when and with what precautions, and it is signed by the person issuing it and the person accepting it. Used properly, it stops dangerous work starting until it is safe to start. Used badly, it is a form signed in the cabin by someone who never saw the job.

By G. Wicks, Crate & Wasteify FounderUpdated 20 October 202610 minute read
Operative in orange coveralls and a face visor grinding steel as sparks fly, with a colleague standing by holding a fire extinguisher and a Crate permit accepted confirmation

The short answer

  • A permit to work is a formal written system for controlling high-risk work. It records the job, the location, the hazards, the precautions, and who issued and accepted it.
  • No UK law requires a permit for every job. But employers must provide safe systems of work, and HSE guidance (HSG250) treats permits as the standard control for hot works, confined spaces, isolations and similar work.
  • A permit does not make a job safe on its own. The checks behind it, the briefing to the team and closing it out properly are what count.
Contents
  1. What is a permit to work?
  2. Is it a legal requirement?
  3. When is a permit needed?
  4. Who does what
  5. The process, step by step
  6. What a permit should include
  7. Common failures
  8. Building Safety Act evidence
  9. Paper or digital?
  10. Sources

What is a permit to work?

A permit to work is a written document that lets named people carry out a specific high-risk job, in a specific place, for a set time, once specific precautions are in place. It sits inside a wider permit to work system: the rules, roles and training that make the paper mean something.

HSE's guidance, HSG250, defines a permit-to-work system as "a formal recorded process used to control work which is identified as potentially hazardous." It also says, just as plainly, "A permit-to-work is not simply permission to carry out a dangerous job."

That second line is the one sites forget. The permit is the end of a process. The work has been planned, the risks assessed, the area checked and the isolations made. The signatures confirm all that has happened. They are not a substitute for it.

HSG250 was written for the petroleum and chemical industries, but it also covers other industries that use permits, and it is the document most UK contractors build their permit procedures on. On site you will hear permits called PTWs, hot works permits, permits to dig or just "the permit for the roof". Same idea.

When is a permit to work needed?

HSG250 says permits suit non-routine work and jobs where different groups need to coordinate. Its list includes work that uses or generates heat, entry into confined spaces, work at height and pressure testing. On a construction site, that usually means the jobs below.

WorkTypical jobsWhy it needs a permitRelated law and guidance
Hot worksWelding, grinding, cutting, brazing and torch-on roofingSparks and heat start fires, sometimes long after the job has finished. A fire watch and a final check are normal hot works permit conditions.CDM 2015 regulation 29 (prevention of risk from fire)
Confined spacesManholes, chambers, tanks, sewers and voidsPoor air, gas and a hard way out. Testing and rescue arrangements have to be in place before anyone goes in.Confined Spaces Regulations 1997
Electrical isolationWork on or near electrical systemsThe system has to be proved dead and isolated so it cannot be switched back on while people are working on it.Electricity at Work Regulations 1989, regulations 12 to 14
Fragile roofsRoof sheets, rooflights and old asbestos cement roofsA fall through a fragile surface is often fatal. Access has to be controlled and protection in place first.Work at Height Regulations 2005, regulation 9 (fragile surfaces)
Digging near buried servicesExcavation, breaking out and ground investigationA struck cable or gas main can kill. Drawings are checked, the ground scanned and safe digging agreed before anyone breaks ground. Often called a permit to dig.CDM 2015 regulations 22 (excavations) and 25 (energy distribution installations), HSE guidance HSG47
Near overhead power linesCranes, tippers, MEWPs, scaffold tubes and long materialsPlant and materials can touch or arc to a live line. Exclusion zones and supervision are agreed before work starts.CDM 2015 regulation 25 (energy distribution installations)
Temporary worksLoading and striking formwork, falsework and propsLoaded too early or struck too soon, temporary works collapse. Permits to load and permits to strike are common on bigger sites.CDM 2015 regulation 19 (stability of structures)

Not every site uses permits for all of these, and some use them for more. Your principal contractor's site rules and the RAMS for the task decide.

1 in 5

Roof work deserves its permit. HSE says almost one in five deaths in construction work involve roof work, and that all roofs should be treated as fragile until a competent person has confirmed they are not.

HSE, roof work guidance for construction

Who does what in a permit to work system?

HSG250 suggests standard titles for each role, so that everyone means the same thing. Your site will probably use different names, such as authorised person, permit issuer or permit receiver. The jobs are the same.

HSG250 roleWhat they doUsually on site
OriginatorAsks for the work to be doneSite manager, package manager or the trade supervisor
Issuing authorityChecks the area and the precautions, then issues the permitA person authorised by the principal contractor to issue permits, often the site manager or a permit coordinator
Permit authoriserGives a second sign-off where an extra level of authorisation is neededA senior manager or specialist, for the highest-risk permits
Performing authorityAccepts the permit for the people doing the workThe supervisor or foreman of the trade doing the job
Permit userWorks under the permit and its conditionsThe operatives
Area authorityControls the place where the work is doneThe site manager, or the client on an occupied or live site
Isolating authorityMakes the isolations and removes them afterwardsAn authorised electrician or engineer
Site checkerCarries out the checks listed on the permitA fire watch, gas tester or other competent person

On most sites the person who issues a permit is not the person who accepts it. That is deliberate. One checks the job is safe to start. The other confirms they understand it and will work to it.

The permit to work process, step by step

Every contractor's procedure is slightly different, but the stages are the same.

  1. Plan the job and assess the risk

    The permit comes from the RAMS, not the other way round. Define the job, the location, the hazards and the controls before anyone picks up a pen.

  2. Raise the permit

    Describe the exact job, the exact location, how long the permit is valid for and the precautions that must be in place. "General hot works, level 3" is how permits stop meaning anything.

  3. Check the area

    The issuer goes to the work area and checks. Isolations made and proved, gas tested, extinguishers in place, combustibles moved, barriers up. Whatever the permit says has been done, someone confirms it has.

  4. Issue and accept

    The issuer signs to say the precautions are in place. The person in charge of the work signs to accept it, confirming they understand the job, the hazards and the precautions. HSG250 is clear that nobody starts a job that needs a permit until one has been authorised and issued.

  5. Brief the team

    Everyone working under the permit needs to know what it says, including what it does not cover. A permit the operatives have never seen is not controlling anything.

  6. Keep it at the job

    The permit, or a copy, stays at the work area. If the job changes, the permit changes. If conditions change, the work stops until someone looks again.

  7. Plan for breaks and shift changes

    If the job runs past a shift, your procedure should say who takes the permit over, how the area is left safe and how work restarts. The next shift does not share your memory.

  8. Close it out

    When the job is finished, the person in charge confirms the work is complete and the area is safe, and the issuer checks before the permit is closed. For hot works that includes a fire check after the work stops.

What should a permit to work include?

If you are writing or reviewing your own permit forms, HSG250 sets out what a permit should contain. On a construction site, a good permit includes:

  • A unique number and the type of permit
  • The exact location, and the plant or equipment involved
  • A clear description of the work, and what it does not cover
  • The hazards, including those from other work nearby
  • The precautions and isolations, and who made them
  • The PPE, gas testing or fire watch required
  • When the permit is valid from and to
  • Signatures of the issuer and the person accepting it, each with the date and time
  • Any other permits or certificates linked to the same job or area
  • The close-out: work complete, area safe, signed and timed

If two permits cover the same area, they should refer to each other. Hot works above an open confined space is two hazards, and each permit holder needs to know about the other.

Common permit to work failures

HSG250's case studies read like a list of things every site manager has seen at least once. Most permit failures come down to the same habits.

  • Signed in the cabinThe issuer never went to the work area. The permit says the combustibles were moved. Nobody checked.
  • Scope creepThe permit was for cutting out one bracket. By dinner it covers half the floor. If the job changes, the permit has to change with it.
  • Blind to what is around itOne HSG250 case study found "the permit made no reference to the surrounding risks." Hot works next to an open solvent store is a different job.
  • Permits nobody can seeAnother found permits "were not displayed at the work sites." If the operative cannot see the permit, it is not controlling the work.
  • Permits that never closeOpen permits pile up and nobody can say which jobs are live and which finished last Tuesday. That is exactly when two trades end up working on the same isolation.
  • A permit instead of planningHSG250 warns a permit "should not be regarded as an easy way to eliminate hazard or reduce risk." The thinking happens before the form, not on it.

Permits and Building Safety Act evidence

Since October 2023, the Building Regulations 2010 in England have required anyone carrying out building work to plan, manage and monitor it so that it complies with all relevant requirements (regulation 11J). On higher-risk buildings, those at least 18 metres or 7 storeys high that have at least two residential units or are hospitals or care homes, government guidance says the principal contractor must "keep evidence that the building work meets building regulations" as part of the golden thread.

Permits are mainly a health and safety control, not a building regulations one. But a dated, signed permit record shows who controlled which work, when and under what conditions. Alongside quality sign-offs and inspection records, it is part of the evidence trail clients and regulators now expect to see.

Paper permit books or digital permits?

Paper permit books work on a small job with one issuer. On a busy site they fall apart. Carbon copies fade, permits leave site in someone's van, and nobody can say at a glance which permits are live. When someone asks who accepted the hot works permit on level 4 six months ago, you are hoping the right book survived.

In Crate, each permit is issued, approved and accepted by the right people, and any permit waiting on someone shows as action required, so it does not sit in a tray waiting for a signature. Every permit keeps a dated record of who did each step, and can be downloaded as a PDF. Operatives sign by QR code, either on the supervisor's screen or on their own phone in the Crate app, which means less queuing at the cabin.

See how permits to work run in Crate, from issue to a dated, signed record.Permits to work in Crate

Sources

  1. HSG250 Guidance on permit-to-work systems, HSE
  2. Why are permit to work systems important?, HSE
  3. Health and Safety at Work etc. Act 1974, section 2, legislation.gov.uk
  4. Construction (Design and Management) Regulations 2015, legislation.gov.uk
  5. Work at Height Regulations 2005, legislation.gov.uk
  6. Electricity at Work Regulations 1989, Part II, legislation.gov.uk
  7. L101 Safe work in confined spaces, HSE
  8. HSG47 Avoiding danger from underground services, HSE
  9. Roof work, HSE
  10. Building Regulations 2010, Part 2A Dutyholders and competence, legislation.gov.uk
  11. Keeping information about a higher-risk building: the golden thread, GOV.UK

Permit to work questions

The questions site teams ask us most, answered straight.

What is a permit to work?

A permit to work is a formal written system for controlling high-risk work. It records the job, the location, the hazards and precautions, and who issued and accepted it, and the work does not start until it is in place.

Is a permit to work a legal requirement in the UK?

No UK law requires a permit for every job. Employers must provide safe systems of work, and for high-risk jobs such as hot works, confined spaces and electrical isolation, HSE guidance treats a permit to work system as the standard way to control them.

What is HSG250?

HSG250 is HSE's guidance on permit-to-work systems. It was written for the petroleum and chemical industries, but it also covers other industries that use permits, and UK contractors widely base their permit procedures on it.

What work needs a permit to work on a construction site?

Hot works, confined space entry, electrical isolation, work on fragile roofs, digging near buried services, work near overhead power lines, and loading or striking temporary works are the most common. Your site rules and RAMS set the full list.

Who can issue a permit to work?

A competent person who has been formally authorised to issue permits, usually by the principal contractor. They should know the work, the site and the hazards, and check the work area themselves before issuing.

Does a permit to work make a job safe?

No. HSE's guidance says the issue of a permit does not, by itself, make a job safe. The planning, the checks at the work area and the briefing to the team are what make it safe.

What is the difference between a permit to work and a risk assessment?

A risk assessment identifies the hazards and the controls needed. A permit to work makes sure those controls are actually in place, at that location, before that specific job starts.

How long is a permit to work valid for?

As long as the permit says, and many sites limit permits to a single shift or working day. If the job runs on, the work changes or conditions change, the permit should be reviewed or reissued.

Permits that are where the work is.

Book a demo and we'll show you permits to work in Crate, from issue to accepted, using your own sites and jobs.