Guide

What is a point of work briefing? And how it differs from a POWRA

A point of work briefing is a short briefing given at the work area, right before a task starts, to check that the job, the place and the people still match the plan. It takes a few minutes. It is the last chance to spot that the ground is wetter, the crane is different or the scaffold tag ran out yesterday, before anyone finds out the hard way.

By G. Wicks, Crate & Wasteify FounderUpdated 20 October 20268 minute read
Site supervisor with a tablet giving a point of work briefing to three operatives beside steel reinforcement at the work area, with the Crate option to issue a point of work briefing

The short answer

  • A point of work briefing (POWB) is a short briefing the supervisor gives at the work area, immediately before a task starts, covering the task, the controls and anything that has changed since the RAMS were written.
  • A POWRA, or point of work risk assessment, is the check the team makes at the same spot to confirm conditions still match the plan. Many sites do both together: brief the team, then check the area.
  • No UK law uses either term, but every contractor must give workers appropriate supervision, instructions and information. If the checks show things have changed, the job stops until the risk is reviewed.
Contents
  1. What is a point of work briefing?
  2. POWB, POWRA, DAB and RAMS
  3. How it differs from a POWRA
  4. Does the law require it?
  5. When to give one
  6. Before-you-start checklist
  7. How to give one
  8. Stopping the job
  9. What to record
  10. Paper or digital?
  11. Sources

What is a point of work briefing?

A point of work briefing, or POWB, is the briefing given where the work will happen, to the people about to do it, just before they start. Not in the cabin at half seven. At the slab edge, the excavation, the riser or the plant room, at the moment the task begins.

It sits at the end of a chain. The RAMS set out how the job should be done. The daily activity briefing covers the whole site's day. The POWB checks that this task, in this spot, right now, still matches what was planned, and that every person in the team knows their part.

Some contractors run one for every task. Most at least use them for higher-risk work: lifting operations, work at height, excavations, hot works, confined spaces, demolition and anything under a permit.

Point of work briefing compared with a POWRA, DAB and RAMS

These four get confused all the time, partly because contractors use the names differently. This is how they usually split.

Briefing or checkWhenWhat it is forWho
Point of work briefing (POWB)At the work area, just before the task startsBriefs the team on the task, the controls and what has changedThe supervisor, to the team doing the task
Point of work risk assessment (POWRA)At the work area, before starting and whenever conditions changeChecks the conditions match the RAMS and records any new hazardsThe team doing the task, often led by the supervisor
Daily activity briefing (DAB)At the start of every shiftThe whole day: work, hazards, interfaces, deliveries and permitsThe supervisor or site manager, to the site team or each gang
RAMS briefingBefore a task first starts, and when the RAMS changeThe agreed method, risks and controls in fullThe supervisor, to everyone doing the task

Some contractors call the POWRA a last minute risk assessment, a Take 5 or a task card. What matters is that each check has a clear job and a record.

How a point of work briefing differs from a POWRA

The two get mixed up because they happen at the same place, at the same time, often on the same bit of paper. They do different jobs.

The point of work briefing is someone telling the team something. The supervisor goes through the task, the sequence, the controls, who does what, and what has changed since the RAMS were briefed.

The point of work risk assessment is the team looking at something. They check the actual area against the plan. Is the access as expected? Is the plant the one in the RAMS? Are the barriers up? Has the weather turned? Any new hazard gets written down, with what is being done about it.

Done well, they run together. Brief, look, agree, start. Done badly, the POWRA becomes a card ticked in the van on the way in, with "no change" written in the same pen for three weeks.

When should you give a point of work briefing?

At minimum, before any task where a change in conditions could seriously hurt someone. Good sites also give one:

  • At the start of every higher-risk task, including anything under a permit
  • When the task moves to a new area or level
  • When someone new joins the team
  • After a break in the work, such as the next morning or after a weather stop
  • When the plant, access equipment or sequence changes
  • After a near miss or incident on a similar task

It does not need to be long. Two or three minutes for a routine task, longer for a complex lift. The length follows the risk.

A point of work briefing checklist

Use these questions at the work area, before anyone starts. If the answer to any of them is no, or not sure, the job waits.

The task

  • Is it the task in the RAMS?
  • Is the current revision of the RAMS here?
  • Does everyone know the sequence?
  • Does everyone know their own part?

The area

  • Is access as planned, and clear?
  • Are barriers and exclusion zones up?
  • Is anyone working above, below or alongside?
  • Are the ground and weather as expected?

The people

  • Has everyone been briefed on the RAMS?
  • Does everyone hold the right cards and training?
  • Is anyone new to the task today?
  • Can everyone follow the briefing?

Plant and equipment

  • Is it the plant named in the RAMS?
  • Have pre-use checks been done?
  • Are inspection tags in date?
  • Is the right PPE here, and does it fit?

Permits and isolations

  • Is the permit issued and in date?
  • Are isolations in place and proved?
  • Are buried services located and marked?

Emergency

  • Is the rescue plan in place, with the kit?
  • Who is the first aider today?
  • Where is the nearest fire point?
  • Does everyone know the way out?

How to give a point of work briefing

The whole thing should take minutes, not half the morning.

  1. Go to the work area with the team

    You cannot brief an exclusion zone properly from the cabin. Stand where everyone can see the edge, the excavation or the load path you are talking about.

  2. Run through the task and the controls

    The sequence, who does what, the controls that matter for this task, and the signals or radio channel you will use.

  3. Check the area together

    Go through the checklist with the team. Ask what looks different from what they expected. The people doing the work often see it first.

  4. Agree what happens if something changes

    Who calls a stop, how, and who they tell. Make it clear that stopping is expected, not a nuisance.

  5. Record it, then start

    Note what was briefed, any changes found and what was done about them. Everyone signs. Then the work starts.

Stopping the job when things have changed

The point of checking at the work area is that sometimes the answer is no. The excavation has water in it. The crane on site is not the one in the lift plan. The scaffold tag expired yesterday. Another trade has started work overhead.

When that happens, the job does not start, or it stops. The supervisor reviews the risk, gets the RAMS revised or the problem put right, and rebriefs the team. That is not lost time. It is what the briefing was for.

The law backs the people who raise it. Section 7 of the Health and Safety at Work etc. Act 1974 puts a duty on every employee "to take reasonable care for the health and safety of himself and of other persons who may be affected by his acts or omissions at work". Regulation 14 of the 1999 Management Regulations requires employees to tell their employer about any work situation they would reasonably consider "represented a serious and immediate danger to health and safety".

Most principal contractors give every worker the authority to stop work they believe is unsafe. A point of work briefing is where you remind people they have it, and mean it.

What to record

The record is short, but it needs to be there. Include:

  • The site, date, task and work area
  • Who gave the briefing
  • The RAMS it relates to, and the revision
  • Changes found at the work area, and what was done about them
  • Who was briefed, each with a signature
  • The time work actually started

Keep it with the RAMS and the permit for the task. If something goes wrong, those three records together show what was planned, what was checked and who was told.

Paper or digital point of work briefings?

Paper briefing sheets and POWRA cards live in pockets and vans. They get filled in after the event, they go missing, and they are hard to tie back to the RAMS and the day they belong to.

In Crate, the supervisor issues the point of work briefing at the work area, right before the task. The team signs by QR code, either on the supervisor's screen after the supervisor scans each operative's passport, or on their own phone in the Crate app. Operatives confirm their start time on their phone, and can open the briefing in their own language and read along as it is delivered.

Each briefing is kept against the site and date, and shows in every operative's passport. It is the kind of dated, signed record that supports your Building Safety Act evidence.

See how point of work briefings work in Crate, from the work area to the signed record.Point of work briefings in Crate

Sources

  1. Construction (Design and Management) Regulations 2015, regulation 15, legislation.gov.uk
  2. Management of Health and Safety at Work Regulations 1999, legislation.gov.uk
  3. Health and Safety at Work etc. Act 1974, section 7, legislation.gov.uk

Point of work briefing questions

The questions site teams ask us most, answered straight.

What is a point of work briefing?

A point of work briefing is a short briefing given at the work area, just before a task starts, to the team about to do it. It covers the task, the controls and anything that has changed since the RAMS were written.

What does POWB stand for?

POWB stands for point of work briefing. It is given at the place the work happens, right before the task starts.

What is the difference between a POWB and a POWRA?

A POWB is the supervisor briefing the team on the task. A POWRA, or point of work risk assessment, is the team checking the work area against the plan and recording any new hazards. Many sites do them together.

Is a point of work briefing a legal requirement?

No UK law uses the term. But under CDM 2015 every contractor must give workers appropriate supervision, instructions and information, and risk assessments must be reviewed when things change. A point of work briefing is a practical way to do both.

Who gives a point of work briefing?

The supervisor or foreman in charge of the task, at the work area. They know the job and can stop it if the checks show something has changed.

How long does a point of work briefing take?

A few minutes for a routine task, longer for a complex lift or a permit task. The length should follow the risk.

What should happen if conditions have changed?

Do not start, or stop. Tell the supervisor, get the risk reviewed and the RAMS revised if needed, and rebrief the team before work starts again.

Do you still need a point of work briefing after a daily activity briefing?

For higher-risk tasks, yes. The daily briefing covers the whole site at the start of the shift. The point of work briefing checks this task, in this place, right before it starts.

The last check before work starts, on record.

Book a demo and we'll show you point of work briefings in Crate, from the work area to the signed record, using your own sites and RAMS.

Book a demo