What is a site issue register? Logging problems on site and closing them out

A site issue register is a single list of every problem on site that needs putting right, with who owns it, how urgent it is, when it is due and whether it has been closed. It turns "someone should sort that" into a name and a date. Without one, issues live in WhatsApp groups, notebooks and the site manager's head, and the head is the first to fill up.

By G. Wicks, Crate & Wasteify FounderUpdated 20 October 20268 minute read
Steel fixer in a white safety helmet and hi-vis vest working on a rebar cage, beside a Crate quality issue marked open and high priority with a due date

The short answer

  • A site issue register is a live list of problems on a construction site that need action: safety hazards, quality defects, damage, missing information and anything else that needs putting right.
  • Each issue needs a description, location, photo, category, priority, owner and due date, and it stays open until someone closes it out with evidence of the fix.
  • It is not a RIDDOR report. Serious injuries, certain diseases and dangerous occurrences have a separate legal duty to report them to HSE.
Contents
  1. What is a site issue register?
  2. Issues, snags and near misses
  3. What to record
  4. Priorities and due dates
  5. Closing issues out
  6. Keep it out of WhatsApp
  7. Does the law require one?
  8. Common mistakes
  9. Paper or digital?
  10. Sources

What is a site issue register?

A site issue register is the list of everything on site that is wrong and needs fixing. A missing handrail on the scaffold. Damaged plasterboard on level 2. A blocked fire exit. A missing cavity barrier. Water coming through the roof. Each one is logged, given an owner and a date, and tracked until it is closed out.

You will also hear it called an issue log, a site issues list or an observation log. Some contractors keep separate registers for safety, quality and environmental issues. Others keep one register with categories. Either works, as long as nothing falls between them.

The register only works if anyone on site can add to it. The operative who spots the problem usually has the best photo and the clearest idea of what is wrong. If logging an issue means walking back to the cabin to find the site manager, it will not get logged.

Issues, snags, defects, near misses and observations

These words get used loosely on site. Here is how they usually differ, and where each one should end up.

TermWhat it meansExampleWhere it usually goes
IssueAnything on site that needs action, whether safety, quality, damage or progressA damaged hoarding panel, a leaking pipe, a missing dimension on a drawingThe site issue register
SnagA minor fault or unfinished item, usually found near the end of a package or at handoverA scuffed door, a missing socket cover, paint on glassA snagging list, often by room or plot
DefectWork that does not meet the drawings, the specification or building regulationsFirestopping not installed to the tested detail, wrong cover to rebarThe issue register, then the defects process in the contract
Near missAn event that could have caused injury or damage but did notA dropped tool landing next to someone, a dumper reversing close to a pedestrianYour near miss or incident reporting process
ObservationSomething spotted that is not a problem yet, or good practice worth notingMaterials stacked close to an edge, a gang keeping a particularly tidy work areaThe issue register or a safety observation scheme

A near miss often creates an issue as well. The dropped tool is the near miss. The missing toe board that let it fall is the issue.

What to record for each issue

An entry in a site issue register should make sense to someone who was not there when it was logged. That means a few fields, filled in properly.

FieldWhat good looks like
ReferenceA unique number, so everyone is talking about the same issue
DescriptionOne clear sentence. "Handrail missing, scaffold lift 3, east elevation" beats "scaffold problem"
LocationLevel, grid, plot or room, precise enough for someone else to walk straight to it
PhotoTaken when the issue is logged, showing the problem and enough of the surroundings to find it
CategorySafety, quality, environmental, damage, design, or whatever your site uses
PriorityHow urgent it is, so the right things get fixed first
OwnerOne named person or company, not "M&E" or "to be confirmed"
Due dateA real date that matches the priority
StatusOpen or completed, with the date it changed
Close-outWhat was done, by whom and when, with a photo of the fix

How to set priorities and due dates

If every issue is urgent, none of them are. Most sites use three or four priority levels. A typical set looks like this.

PriorityWhat it meansTypical response
ImmediateDanger to people right nowMake it safe or stop the work before you leave the area, then log it
HighCould cause harm or serious damage soon, or will hold up the jobSame day or next working day
MediumNeeds fixing, but nobody is at risk in the meantimeWithin the week
LowMinor, cosmetic or tidy-up itemsBy the end of the package or at a set review

If something is genuinely dangerous, logging it is not enough. Make it safe first, then log it. The register tracks the fix. It does not make the area safe.

How to close out an issue properly

Logging issues is the easy part. Closing them out, with proof, is where most registers fall down.

  1. Give it one owner

    One person or one company. An issue owned by everyone is owned by no one.

  2. Agree what fixed looks like

    Replace the handrail, or replace it and inspect the whole lift? Agree it up front and nobody argues at close-out.

  3. Fix it and photograph it

    Take the close-out photo from roughly where the original was taken, so the two can be compared side by side.

  4. Have someone else check it

    For anything to do with safety or compliance, the person who fixed it should not be the only one who says it is fixed.

  5. Close it with a date

    Mark it completed, with who closed it and when. Then tell the person who raised it. Nothing encourages reporting like seeing problems get fixed.

  6. Look for patterns

    Ten housekeeping issues against the same subcontractor in a month means a conversation with their supervisor, not ten more close-outs.

Then review the register every week, at the progress meeting or the subcontractor meeting. Overdue items first, then high priority, then anything that has been open longer than a month. Ten minutes a week keeps the list honest. Leave it a quarter and you will spend a day working out which of the 300 open issues still exist.

Keep it out of the WhatsApp group

Most sites have a WhatsApp group, and most site issues get mentioned there first. That is fine for telling people. As a register, it is useless.

  • Issues scroll away under delivery updates and the weekend football
  • Nobody is assigned, so everybody assumes somebody else is dealing with it
  • There is no due date, no status and no way to see what is still open
  • When someone leaves the job or the group, their photos and messages leave too
  • Personal phones are a poor place to keep site records, and a data protection headache
  • Six months later, nobody can prove when something was reported or when it was fixed

Use the group to say you have logged it. Use the register to log it.

Common site issue register mistakes

Most registers that fail do so in the same few ways.

  • Only the site manager can log issuesThe person who found the problem has to go and find someone to write it down. Most of the time they will not bother.
  • Vague descriptions"Scaffold issue" tells the scaffolder nothing. Location, problem, photo.
  • Everything is high priorityThen nothing is. Use the levels honestly and the urgent things stand out.
  • Closed without evidenceA thumbs-up from someone in a van is not a close-out. Get a photo of the fix.
  • The register becomes a graveyardHundreds of open issues nobody has looked at in months. Review it every week, then close or chase.
  • Using it to blame peopleIf logging an issue gets someone shouted at, people stop logging issues. The problems do not stop.

A spreadsheet or a digital site issue register?

A spreadsheet on the site manager's laptop beats a notebook. But only one person can update it, the photos live somewhere else, and the operative who spotted the problem still has to find someone to tell.

In Crate, anyone on site can log an issue from their phone, and it gets a reference straight away. Each issue has a category, a priority and a due date, and shows as open until it is completed, with its full history kept against it. Any issue's record can be downloaded as a PDF when a client, an auditor or a regulator asks to see it.

See how the site issue register works in Crate, from logged on a phone to completed.Issue register in Crate

Sources

  1. Construction (Design and Management) Regulations 2015, regulations 13 and 15, legislation.gov.uk
  2. Building Regulations 2010, Part 2A Dutyholders and competence, legislation.gov.uk
  3. Keeping information about a higher-risk building: the golden thread, GOV.UK
  4. RIDDOR: who should report?, HSE
  5. RIDDOR: types of reportable incidents, HSE

Site issue register questions

The questions site teams ask us most, answered straight.

What is a site issue register?

A site issue register is a live list of problems on a construction site that need putting right. Each issue has a location, photo, priority, owner and due date, and is tracked until it is closed out.

What is the difference between an issue and a snag?

An issue is anything on site that needs action, at any stage of the job. A snag is a minor fault or unfinished item, usually picked up near the end of a package or at handover.

Who should log issues on site?

Anyone on site who spots a problem. The register works best when operatives can log issues themselves, from where they are, rather than having to find the site manager.

What should be recorded for each issue?

A reference, a clear description, the exact location, a photo, a category, a priority, one owner, a due date, the status, and the close-out with evidence of the fix.

How should site issues be prioritised?

Most sites use three or four levels, from immediate danger that is made safe on the spot down to low priority tidy-up items. Due dates should match the priority.

Is a site issue register a legal requirement?

No law uses the term. But CDM 2015 requires principal contractors and contractors to plan, manage and monitor their work, and in England the Building Regulations 2010 require principal contractors to plan, manage and monitor building work so that it complies. A register is a simple way to show you do.

Does logging an accident in the issue register count as a RIDDOR report?

No. RIDDOR is a separate legal duty to report certain injuries, diseases and dangerous occurrences to HSE. Your issue register should feed your incident process, not replace it.

Why not report site issues in a WhatsApp group?

A WhatsApp group is fine for telling people about a problem, but it has no owners, due dates or status, and photos and messages leave with the people who sent them. Log the issue in the register and use the group to say it has been logged.