What is RAMS? Risk assessments and method statements explained
RAMS is short for risk assessment and method statement, the document that sets out the risks of a job and the safe way to do it, step by step. Almost every UK principal contractor wants one before you start. Most are too long, too generic and signed by people who have never read them. That part is fixable.

The short answer
- RAMS stands for risk assessment and method statement. The risk assessment sets out what could hurt people on a task and the controls needed. The method statement sets out, in order, how the job will be done safely.
- Risk assessment is a legal duty under regulation 3 of the Management of Health and Safety at Work Regulations 1999. A method statement is not generally required by law, but HSE recognises it as an effective way to plan the work and communicate the safe system of work.
- A good RAMS is specific to the site and task, briefed to everyone doing the work before they start, signed, and revised when the job changes.
Contents
What is RAMS?
RAMS stands for risk assessment and method statement. It is two documents, usually bound into one, written for a specific task: erecting a scaffold, pouring a slab, cutting in a new opening, fitting out a plant room.
The risk assessment answers what could go wrong and how bad it would be. Falls from the slab edge, silica from cutting, a dropped load during a lift. For each one, it sets out the controls.
The method statement answers how the job will actually be done. Step by step, in order, with the people, plant, permits and controls at each stage. HSE describes it as setting out "in a logical sequence exactly how a job is to be carried out in a way that secures health and safety and includes all the control measures".
The contractor doing the work writes it. The principal contractor reviews it before work starts. The operatives are the ones who need to understand it, and that is where most RAMS fall down.
Is RAMS a legal requirement?
Half of it is. The risk assessment is a legal duty for every employer.
"Every employer shall make a suitable and sufficient assessment of the risks to the health and safety of his employees to which they are exposed whilst they are at work"
Management of Health and Safety at Work Regulations 1999, regulation 3(1)(a)
The same regulation covers people outside your business who could be affected by your work, which on a construction site means other trades, visitors and the public walking past the hoarding. Where you employ five or more people, regulation 3(6) says you must record "the significant findings of the assessment". Some regulations ask for specific assessments on top, including work at height, COSHH, manual handling, noise, vibration and lead.
The method statement is different. HSE is clear about it:
"While not required by law, method statements are also prepared for many other construction activities and are proven to be an effective and practical way to help plan, manage and monitor construction work."
HSE, construction guidance on administration
The "other" is there because of one exception HSE points to. The arrangements for demolition, dismantling or structural alteration "must be recorded in writing before the work begins", and that is usually done with a method statement.
In practice the distinction rarely matters. Principal contractors make RAMS a condition of starting work, clients write them into contracts, and under CDM 2015 every contractor must give their workers "appropriate supervision, instructions and information" (regulation 15(8)). A method statement briefed to the gang is the most common way to do that, and to prove it.
This is general guidance, not legal advice. Take advice on how the duties apply to your business and your projects.
What goes in a RAMS?
There is no set format, and there should not be. But a risk assessment and method statement that is any use on site covers these, in roughly this order.
| Section | What it should cover | Where it usually goes wrong |
|---|---|---|
| Task and location | What the job is, where on site, and what is out of scope | A scope so vague it could describe any job on any site |
| Sequence of work | Each step in the order it will be done, with diagrams where they help | A list of good intentions instead of a sequence |
| Hazards | The risks from the risk assessment that apply to this task, in this place | Every hazard known to construction, copied in |
| Controls | What will be done about each hazard, and who does it | Controls nobody on site has the kit for |
| People and competence | Who is doing the work, who supervises, and the cards and training needed | Names left over from the last job |
| Plant, equipment and substances | What is being used, its inspections and the COSHH assessments | A 3 tonne excavator in the RAMS, a 13 tonne on site |
| Permits and interfaces | Permits needed, other trades affected and exclusion zones | No mention of the gang working underneath |
| Emergency and rescue | First aid, emergency arrangements and task-specific rescue, such as a stranded MEWP | "Call 999" as the rescue plan for work at height |
| Environment | Dust, noise, waste, spills and protecting drains | Left out entirely |
| Review and sign-off | Who wrote it, who approved it, the revision, the date and who has been briefed | No revision number, so nobody knows which copy is current |
Generic RAMS versus site-specific RAMS
A generic RAMS is a contractor's standard document for a type of work, written once and used on every job. There is nothing wrong with having one. HSE accepts that "if a similar operation is repeated, the statement will be similar from job to job".
The problem is sending the generic one to site as if it were finished. It does not know the access route, the ground conditions, the overhead cables, the trades working nearby or where the nearest A&E is. The site-specific part is where the real risks live.
To turn a generic RAMS into a site-specific RAMS, check it against the site. Walk the area, read the construction phase plan and the site rules, talk to the principal contractor about interfaces, and change whatever does not fit. If you cannot point to anything that changed, it is still generic.
How long should a RAMS be?
As long as the job needs and no longer. Nobody briefs an 80-page RAMS. They hold it up, say it's all in there, and pass the pen round.
Long RAMS are usually long for the wrong reasons: company policies pasted in, every hazard on the list ticked just in case, CVs and certificates bound into the middle. They are written for the file and the reviewer, not for the people doing the work.
The test is simple. Could the supervisor brief the method and the main controls from it in ten minutes, with the gang still listening? If not, move the background to an appendix and keep the front pages about the task. HSE notes that the most effective method statements often include diagrams. A sketch of the lift sequence beats three pages describing it.
How to brief and sign RAMS
A RAMS protects nobody until the people doing the job understand it. Here is how to brief one properly.
Check it against the job first
The supervisor reads it on site, against the actual work area, before the briefing. If the method no longer matches the job, stop and get it revised.
Brief it before the task starts
Brief everyone doing the task, at or near the work area, before they start. Not after lunch, and not on Friday for the week.
Walk through the sequence and the controls
Talk through the steps in order and the controls that matter, using the drawings and sketches. Leave the boilerplate in the document.
Check it was understood
Ask someone to explain the exclusion zone or the rescue plan back to you. If they can't, brief it again, differently.
Get everyone signed, including late starters
Each person signs to confirm they were briefed on that revision. Anyone joining the task later is briefed before they start, not when someone remembers.
Rebrief when it changes
A new revision means a new briefing. Signatures on revision 2 do not cover revision 3.
When should RAMS be reviewed and revised?
The law sets the trigger. Regulation 3(3) says a risk assessment must be reviewed if "there is reason to suspect that it is no longer valid" or "there has been a significant change in the matters to which it relates", and changed where the review shows it needs to be. On site, that usually means:
- Different plant or access equipment from the one planned
- Ground, weather or site conditions that do not match the plan
- A change in the sequence or the method
- A new trade working nearby, above or below
- A near miss, incident or safety alert that affects the task
Each revision needs a number and a date, and the old copies need to come out of circulation. The most dangerous RAMS on site is the old revision still in the van.
On higher-risk buildings, at least 18 metres or 7 storeys with at least 2 residential units, or hospitals and care homes, principal contractors must also keep evidence that the work meets building regulations and manage change control. Dated RAMS revisions, with a record of who was briefed on each one, are the kind of record that supports that evidence. Building Safety Act competence duties apply to all building work, higher-risk or not.
Common RAMS failures
Most RAMS that fail on site fail in the same few ways.
- Copy and pasteAnother site's name on page four, a client who is not yours, a crane that left site last month. Reviewers spot it, and so does anyone investigating an accident.
- Written by someone who has never seen the jobA RAMS written in an office from a drawing misses what you only see on site: the slope, the overhead line, the gang already working there.
- Signed but never briefedA pen passed round the cabin is not a briefing. The signature should mean the person was told the method, understood it and agreed to work that way.
- One method on paper, another on siteIf the gang has found a better way, update the RAMS. If they have found a quicker, riskier way, stop the job. Either way, the paper and the work should match.
Paper or digital RAMS?
On most sites, RAMS still travel as emailed PDFs. They get printed, read out in the cabin and signed on a sheet stapled to the back. Revisions go round by email and old copies stay in vans. When someone asks who was briefed on which revision, it means digging through folders.
In Crate, each task has its own RAMS briefing. Operatives are briefed and sign before work starts, by QR code on the supervisor's screen after the supervisor scans their passport, or on their own phone in the Crate app. Every version is kept, and updating a template does not change briefings already issued, so the record shows what people were actually briefed on.
Operatives see a condensed version of the RAMS on their own phone, in their own language, with the full RAMS attached. Your team still writes the RAMS. Crate gets it in front of the people doing the job, in a language they understand, and keeps the record.
Sources
- Management of Health and Safety at Work Regulations 1999, legislation.gov.uk
- Construction: administration, risk assessments and method statements, HSE
- Construction (Design and Management) Regulations 2015, regulation 15, legislation.gov.uk
- Keeping information about a higher-risk building: the golden thread, gov.uk
RAMS questions
The questions site teams ask us most, answered straight.
What is RAMS?
RAMS stands for risk assessment and method statement. It is the document that sets out the risks of a specific task, the controls, and the step-by-step method for doing the work safely.
What does RAMS stand for in construction?
RAMS stands for risk assessment and method statement. The two are usually written as one document for a specific task.
Is RAMS a legal requirement in the UK?
The risk assessment is. Regulation 3 of the Management of Health and Safety at Work Regulations 1999 requires every employer to assess the risks, and to record the significant findings if they employ five or more people. A method statement is not generally required by law, but most principal contractors will not let work start without one.
What is the difference between a risk assessment and a method statement?
The risk assessment identifies what could cause harm and the controls needed. The method statement sets out, in order, how the job will be done safely with those controls in place.
Who writes RAMS?
The contractor doing the work, through someone competent who knows the task and has seen the site. The principal contractor usually reviews and accepts it before work starts.
How long should a RAMS be?
As long as the task needs and no longer. A supervisor should be able to brief the method and the main controls from it in about ten minutes.
When should RAMS be reviewed?
When there is reason to think the assessment is no longer valid or there has been a significant change, such as different plant, new site conditions, a change in sequence or a near miss. Brief every revision to the people doing the work.
Do workers have to sign RAMS?
No law requires a signature, but a signed record is the usual evidence that each person was briefed on the current revision before starting work.
More on RAMS and site briefings
RAMS sit alongside the permits and briefings that control the work every day.
RAMS
Brief each RAMS, get it signed and keep every version.
What is a point of work briefing?
Final checks at the work area, right before the task.
What is a permit to work?
How permits control high-risk work on site.
What is a daily activity briefing?
The start-of-shift briefing on the day's work.
RAMS that get read, briefed and signed.
Book a demo and we'll show you RAMS briefings in Crate, from issue to signed record, using your own sites and tasks.